5d. Install straps on phases A and C.

 Place the FG 

frame straps [5] over the carriage bolts and antiturn 
clips, as shown in Figures 16 and 17. Place conical 
washers [7] on the bolts and secure with nuts [11]. 
Leave the connections finger tight. Go to step 6 to 
install the mounting brackets. 

 

Figure 16. Installing straps on phases A and C. 

Figure 16. Installation des brides sur des phases A et C. 

5e.  Install carriage bolt assemblies on phases B and C.

 

Position the carriage bolt [14] and antiturn clip [4] 
assemblies as shown in Figures 18 and 19. 

 

Figure 18. Installing carriage bolt assemblies on phases B and 

C. 

Figure 18. Installation des assemblages de boulon de 

carrosserie sur des phases B et C. 

5f.  Install straps on phases B and C.

 Place the FG 

frame straps [5, 6] over the carriage bolts and antiturn 
clips, as shown in Figures 20 and 21. Place conical 
washers [7] on the bolts and secure with nuts [11]. 
Leave the connections finger tight. Go to step 6 to 
install the mounting brackets. 

 

Figure 20. Installing straps on phases B and C. 

Figure 20. Installation des brides sur des phases B et C. 

5d.  Installer les brides sur des phases A et C.

 Placer les 

brides de cadre FG [5] sur les boulons de carrosserie 
et les clips immobilisés, tel que montré aux Figures 16 
et 17. Placer les rondelles cuvettes [7] sur les boulons 
et fixer avec des écrous [11]. Serrer les connexions à 
la main. Aller à l’étape 6 pour installer les supports de 
fixation. 

 

Figure 17. Installing straps on phases A and C, isometric view. 

Figure 17. Vue isométrique de l’installation des brides sur des 

phases A et C. 

5e.  Installer les assemblages de boulon de carrosserie 

sur des phases B et C.

 Positionner les assemblages 

de boulon de carrosserie [14] et de clip immobilisé [4] 
tel que montré aux Figures 18 et 19. 

 

Figure 19. Installing carriage bolt assemblies on phases B and 

C, isometric view. 

Figure 19. Vue isométrique de l’installation des assemblages 

de boulon de carrosserie sur des phases B et C. 

5f.  Installer les brides sur des phases B et C.

 Placer les 

brides de cadre FG [5, 6] par-dessus les boulons de 
carrosserie et les clips immobilisés tel que montré aux 
Figures 20 et 21. Placer les rondelles cuvettes [7] sur 
les boulons et les fixer avec des écrous [11]. Serrer les 
connexions au doigt. Aller à l’étape 6 pour installer 
les supports de fixation. 

 

Figure 21. Installing straps on phases B and C, isometric view. 

Figure 21. Vue isométrique de l’installation des brides sur des 

phases B et C. 

 

6

 

Summary of Contents for Spectra Series AMCB6FGB

Page 1: ...ue AMCB6FGB et AMCB4FGB Ces kits sont pour utilisation de disjoncteurs de types FGH FGL FGN et FGP Utiliser le kit de couvercle de disjoncteur de numéro de catalogue AFP4FGD Installation AVERTISSEMENT Danger de choc électrique ou de blessure Mettre le courant en avant du panneau de distribution ou du tableau de contrôle à Off avant de travailler à l intérieur de l équipement ou d en retirer toute ...

Page 2: ...ste des pièces pour les kits AMCB4FGB et AMCB6FGB 2 Locate the side of the interior with a 2 75 inch reference distance The circuit breaker straps are mounted on the side of the panel interior bus at which the distance from the vertical bus face to the inner face of the bus support rail is 2 75 inches as indicated in Figure 2 3 Assemble antiturn clips onto carriage bolts Slide an antiturn clip 4 o...

Page 3: ...ight Go to step 6 to install the mounting brackets G9 Figure 9 Installing the straps for three phase connections isometric view Figure 9 Vue isométrique de l installation des brides pour des connexions trois phases La Figure 5 illustre les configurations possibles de courroies de barre omnibus pour les étapes suivantes 4 Installations trois phases Utiliser la procédure suivante pour toutes les ins...

Page 4: ...ble bus strap combinations Figure 5 Combinaisons possibles de brides de barre omnibus 5 Two pole installations Use the following procedure for all two pole installations kit AMCB4FGB For installations using phases A and B continue with step 5a For installations using phases A and C go to step 5c For installations using phases B and C go to step 5e 5 Installations deux pôles Utiliser la procédure s...

Page 5: ...lages de boulon de carrosserie sur des phases A et B Positionner les assemblages de boulon de carrosserie 14 et de clip immobilisé 4 tel que montré aux Figures 10 et 11 Figure 11 Installing carriage bolt assemblies on phases A and B isometric view Figure 11 Vue isométrique d assemblage de boulons de carrosserie sur des phases A et B 5b Installer les brides sur des phases A et B Placer les brides d...

Page 6: ...A et C Placer les brides de cadre FG 5 sur les boulons de carrosserie et les clips immobilisés tel que montré aux Figures 16 et 17 Placer les rondelles cuvettes 7 sur les boulons et fixer avec des écrous 11 Serrer les connexions à la main Aller à l étape 6 pour installer les supports de fixation Figure 17 Installing straps on phases A and C isometric view Figure 17 Vue isométrique de l installatio...

Page 7: ...rail latéral du panneau avec des vis auto taraudeuses 1 tel que montré à la Figure 22 Serrer les vis à 30 po lb 7 Installer les disjoncteurs Positionner la barrière par dessus le support de fixation tel que montré à la Figure 23 Positionner les disjoncteurs de manière à ce que les terminaux du côté ligne ou On reposent sur les blocs de contact sous jacents des brides et que les côtés opposés soien...

Page 8: ...l autre dérivation laissée ouverte pour future utilisation En ce cas isoler les surfaces exposées des blocs de contact des brides dans la dérivation inutilisée Couvrir les surfaces de contact avec deux couches de ruban thermoplastique reconnu UL 105 C OANZ2 tel que Permacel P 30 105 ou 3M 66R afin d obtenir une épaisseur minimale d isolation de 0 013 pouce These instructions do not cover all detai...

Reviews: