P50 Agile P253
6 Protection Functions
P253/EN M/C
6-21
2.8.1
Sensitive Earth Fault Protection (ordering option)
Sensitive Earth Fault protection is an ordering option and is implemented in the
EARTH FAULT 1
column of the relevant settings group.
The product provides three stages of SEF protection with independent time delay characteristics.
Stages 1, 2 and 3 provide a choice of operate and reset characteristics, where you can select
between:
•
A range of standard IDMT (Inverse Definite Minimum Time) curves
•
DT (Definite Time)
This is achieved using the cells
•
IN1>(n) Function
for the overcurrent operate characteristic
•
IN1>(n) Reset Char
for the overcurrent reset characteristic
where (n) is the number of the stage.
Stages 1, 2 and 3 also provide a Timer Hold facility. This is configured using the cells
IN1>(n) tRESET
.
2.9
Restricted Earth Fault Protection
Winding-to-core faults are quite common due to insulation breakdown. Such faults can have very low
fault currents, but they are faults nevertheless and have to be picked up, as they can still severely
damage expensive equipment. Often the fault currents are even lower than the nominal load current.
Clearly, neither overcurrent nor percentage differential protection is sufficiently sensitive in this case.
We therefore require a different type of protection arrangement. Not only should the protection
arrangement be sensitive, but it must create a protection zone, which is limited to the
transformer/Motor/Generator windings. Restricted Earth Fault (REF) protection satisfies these
conditions. The high-impedance measurement principle is a sensitive method for detecting earth
faults. It can be applied to transformers, motors, generators and reactors when these are operated on
an earthed network.
Application of REF protection is explained by means of an example.
The figure below shows an REF protection arrangement for the star connected winding. The current
transformers measuring the currents in each phase are connected in parallel. In this arrangement the
phase currents and the zero sequence current in the neutral line is measured. We know that an
external unbalanced fault causes zero sequence current to flow through the neutral line, resulting in
uneven currents in the phases, which would cause the IED to maloperate. By measuring this zero
sequence current and placing the current transformer in parallel with the other three the currents are
balanced up resulting in stable operation.
Now only a fault inside the star connected winding can create an imbalance sufficient to cause the IED
to issue a trip command.
Summary of Contents for P50 Agile P253
Page 3: ...P50 Agile P253 1 Introduction P253 EN M C 1 1 INTRODUCTION CHAPTER 1 ...
Page 4: ...1 Introduction P50 Agile P253 1 2 P253 EN M C ...
Page 11: ...SAFETY INFORMATION CHAPTER 2 ...
Page 12: ...Safety Information Pxxx 2 ...
Page 23: ...P50 Agile P253 3 Hardware Design P253 EN M C 3 1 HARDWARE DESIGN CHAPTER 3 ...
Page 24: ...3 Hardware Design P50 Agile P253253 3 2 P253 EN M C ...
Page 28: ...3 Hardware Design P50 Agile P253253 3 6 P253 EN M C E00276 Figure 2 Hardware design overview ...
Page 32: ...3 Hardware Design P50 Agile P253253 3 10 P253 EN M C ...
Page 33: ...P50 Agile P253 4 Front Panel P253 EN M C 4 1 FRONT PANEL CHAPTER 4 ...
Page 34: ...4 Front Panel P50 Agile P253 4 2 P253 EN M C ...
Page 39: ...P50 Agile P253 4 Front Panel P253 EN M C 4 7 Figure 2 USB port ...
Page 40: ...4 Front Panel P50 Agile P253 4 8 P253 EN M C ...
Page 41: ...P50 Agile P253 5 Configuration P253 EN M C 5 1 CONFIGURATION CHAPTER 5 ...
Page 42: ...5 Configuration P50 Agile P253 5 2 P253 EN M C ...
Page 154: ...5 Configuration P50 Agile P253 5 114 P253 EN M C ...
Page 155: ...P50 Agile P253 6 Protection Functions P253 EN M C 6 1 PROTECTION FUNCTIONS CHAPTER 6 ...
Page 156: ...6 Protection Functions P50 Agile P253 6 2 P253 EN M C ...
Page 182: ...7 Protection Parameter Settings P50 Agile P253 7 2 P253 EN M C ...
Page 203: ...P50 Agile P253 8 Monitoring Control P253 EN M C 8 1 MONITORING CONTROL CHAPTER 8 ...
Page 204: ...8 Monitoring Control P50 Agile P253 8 2 P253 EN M C ...
Page 222: ...8 Monitoring Control P50 Agile P253 8 20 P253 EN M C ...
Page 223: ...P50 Agile P253 9 SCADA Communications P253 EN M C 9 1 SCADA COMMUNICATIONS CHAPTER 9 ...
Page 224: ...9 SCADA Communications P50 Agile P253 9 2 P253 EN M C ...
Page 249: ...P50 Agile P253 10 Installation P253 EN M C 10 1 INSTALLATION CHAPTER 10 ...
Page 250: ...10 Installation P50 Agile P253 10 2 P253 EN M C ...
Page 260: ...11 Commissioning Instructions P50 Agile P253 11 2 P253 EN M C ...
Page 270: ...11 Commissioning Instructions P50 Agile P253 11 12 P253 EN M C ...
Page 272: ...12 Maintenance and Troubleshooting P50 Agile P253 12 2 P253 EN M C ...
Page 282: ...13 Technical Specifications P50 Agile P253 13 2 P253 EN M C ...
Page 292: ...13 Technical Specifications P50 Agile P253 13 12 P253 EN M C ...
Page 293: ...P50 Agile P253 14 Wiring Diagrams P253 EN M C 14 1 WIRING DIAGRAMS CHAPTER 14 ...
Page 294: ...14 Wiring Diagrams P50 Agile P253 14 2 P253 EN M C ...
Page 297: ......