Installation of the Gasboy 9820 Pump Interface Kit

Page 6

MDE-4864B Gasboy® 9820 Pump Interface Kits Installation Instructions · March 2022 

3

Loosen the two screws located on the left and right display support brackets and pivot the 
Display Assembly down.

Figure 2: Relocating the Display Assembly

Loosen 
the 
Screws

Tag the 
Wires

4

Note down the wiring or tag all the wires that are connected to the terminal blocks. Remove all 
the wires from the terminal blocks.

5

If the model 9820 Pump contains a battery-backed power supply, pull the connector off P1 on 
the power supply. After a few seconds, reconnect P1.

6

Remove the 9820 Chassis from the cabinet.

7

Install the PC Board using the #6-32 hardware.

Figure 3: Installing the PC Board

CHASSIS TOP VIEW

Cable

#6-32 Hardware

PC Board

Summary of Contents for 9820

Page 1: ...llation of the kit Flat tip Screwdriver Cross tip Screwdriver Standard Socket set Parts List The following table lists the parts included in the Pump Interface Kits Sr No Description Part Number Quant...

Page 2: ...n and Operation Manual Gasboy Atlas Pumps Dispensers MDE 4652 Atlas 9800 Electronics Field Installation Instructions Gasboy Atlas Pumps Dispensers Abbreviations and Acronyms Term Description DEF Diese...

Page 3: ...lations must be followed Failure to install inspect maintain or service this equipment in accordance with these codes regulations and standards may lead to legal citations with penalties or affect the...

Page 4: ...n IMPORTANT Oxygen may be needed at scene if gasoline has been ingested or inhaled Seek medical advice immediately Lockout Tagout Lockout Tagout covers servicing and maintenance of machines and equipm...

Page 5: ...m Refer to MDE 4567 9120K 9820K Series AST Pumps Installation and Operation Manual and your Fuel Management System Installation Manual before proceeding To install the Gasboy 9820 Pump Interface Kit p...

Page 6: ...Assembly Loosen the Screws Tag the Wires 4 Note down the wiring or tag all the wires that are connected to the terminal blocks Remove all the wires from the terminal blocks 5 If the model 9820 Pump co...

Page 7: ...ed wire in position 1 Secure the terminal block using the 8 32 hardware Figure 4 Installing the Terminal Block Chassis Cable 8 32 Hardware 9 Carefully route the cable and install the connector on P1 o...

Page 8: ...fer to MDE 4652 Atlas 9800 Electronics Field Installation Instructions The table below shows the jumper settings and terminal block positions to connect at the bottom of the register based on the conf...

Page 9: ...puts from a single pulser Figure 5 Dual channel Single hose Pulse out I F REMOTE REGISTER Notes 1 All wiring and conduit runs must conform with all building fire codes all Federal State and Local code...

Page 10: ...and are for identification purposes only Use of these names logos and brands does not imply endorsement 2022 GASBOY 7300 West Friendly Avenue Post Office Box 22087 Greensboro North Carolina 27420 Phon...

Reviews: