Assembly instructions for fitters /
Load balancing for multiple chargers in group
Assembly instructions for fitters /
Load balancing for multiple chargers in group
To activate load balancing in a group, a GARO Modbus energy meter must be installed
in the supply distribution box. The following energy meters are approved:
•
GNM1D-RS485 (single-phase Modbus)
•
GNM3D-RS485 (three-phase Modbus)
The meter's Modbus address must be set to 100.
The energy meter continually measures the total energy consumption for each phase.
Data is transmitted to the first wallbox (GLB Master), which controls the charging current
per phase for the entire system in order to prevent the main fuses from tripping. When
using a single-phase energy meter, the meter must be set to the same phase as all of the
wallboxes.
A maximum of 32 wallboxes may be connected by a shielded twisted pair cable, which
is connected to the wallbox connection block labelled ‘Data Link’.
It is not permitted to form a cascade from a box which leads out to the charger using one
or more parallel connected drop cables. See the installation example to the right.
The Data Link cable must be electrically terminated in the first and final wallboxes, via
DIP switch SW1 (DIP6) on the printed circuit board. In the below example, the SW1 (DIP
6) DIP switch is to be set to ‘ON’ in wallboxes no. 1 and 5, and ‘OFF’ in the remaining
boxes.
To verify that the master wallbox is defined as master, ensure the SW1 switch (DIP 5) is
set to ‘ON’ mode.
Load balancing for multiple chargers in group
Final resistor ‘Datalink’ ON=activated: OFF=deactivated
GLB mode ON=Master: OFF=Slave
SW1
E-meter
Parttvinnad kabel
Laddbox 1
GLB
Wi-Fi
GLB
Standard
Laddbox 2
Laddbox 3
Data Link
Data Link
Data Link
Data Link
Elcentral
Energimätare
0000.0
Data Link
Kabel: ELAKY/ELAKY
-
S 2x2x0.6
eller liknande
Parttvinnad
Laddbox 4
Laddbox 5
GLB Standard
GLB Standard
GLB Standard
Adress 100
ON
ON
ON
ON
ON
6
5
MASTER
SLAVE
SLAVE
SLAVE
SLAVE
Par
tt
vinnad
0000.0
Elcentral
Par
tt
vinnad
Kopplingsdosa
Kopplingsdosa
Kopplingsdosa
Kopplingsdosa
GLB Wi-Fi
GLB Standard
GLB Standard
GLB Standard
GLB Standard
Laddbox 1
Laddbox 2
Laddbox 3
Laddbox 4
Laddbox 5
E-meter
Data Link
Data Link
Data Link
Data Link
Data Link
Kabel: ELAKY/ELAKY-S 2x2x0.6
eller liknande
Adress 100
ON
ON
ON
ON
ON
6
5
MASTER
SLAVE
SLAVE
SLAVE
SLAVE
Example of installation – Data Link, direct connection between wallboxes
Example of installation – Data Link, permitted connection via external junction
boxes
It should be noted that SW1 (DIP 1–3) does not have a function for group load
balancing. Instead, group balancing is performed in the GLB Master's web interface (see
section entitled Load balancing settings in the web interface).
(figure 15)
(figure 16)
(figure 17)