GSB 15 Installation Manual
Rev. 3
Page 4-1
4 POST INSTALLATION CONFIGURATION & CHECKOUT
4.1 Mounting, Wiring, and Power Checks
Verify all cables are properly secured and shields are connected to the ground lug located on the back of
the unit. Check the movement of the flight and engine controls to verify there is no interference between
the cabling and control systems. Verify all wiring is installed as described in this manual. Prior to installing
and powering up the GSB 15, the wiring harness must be checked for proper connections to the aircraft
systems and other avionics equipment. Point to Point continuity must be checked to expose any faults such
as shorting to ground or wiring discrepancies. Any faults or discrepancies must be corrected before
proceeding. After accomplishing a continuity check, perform power and ground checks to verify proper
power distribution to the GSB 15. Any faults or discrepancies must be corrected at this time. The GSB 15
can be installed after completion of the continuity and power checks.
4.2 Configuration Setup
Not applicable.
4.3 Diagnostic Information
Not applicable.
4.4 Ground Checks
Not applicable.
4.5 Software Loading Procedure
The GSB 15 does not use or load its own operating software.