background image

Part # 1382684 (01/08)

Page 7

Gas Supply

Before assembly and connection check the gas supply . 

1 .  The type of gas for which the unit is equipped is stamped 

on the data plate located behind the drip tray . Connect 

a unit stamped “NAT” only to natural gas; connect those 

stamped “PRO” only to propane gas .

2 .  If it is a new installation have the gas authorities check 

the meter size and piping to assure that the unit is 

supplied with sufficient amount of gas pressure required 

to operate the unit .

3 .  If it is an additional or replacement equipment have the 

gas authorities check the pressure to make certain that 

the existing meter and piping will supply fuel to the unit 

with not more than 1/2” water column pressure drop . 

WARNING:  Check gas connections for leaks . Use a soap 

solution or similar means . 

DO NOT USE AN OPEN FLAME

 .

NOTE:  This appliance is not recommended for residential 

installation .

Ventilation and Air Supply

Proper ventilation is highly important for good operation . 

The ideal method of ventilation for a Salamander broiler is 

the use of a properly designed canopy hood, which should 

extend six (6”, 152 mm) beyond all sides of the appliance and 

six (6) feet six (6) inches (1981 mm) from the floor .

A strong exhaust fan will create a vacuum in the room . For an 

exhaust system to work properly, replacement air must enter 

the room in which the vent is located . The amount of air that 

is exhausted must equal the amount entering, (make-up air) .

INSTALLATION continued

All gas burners and pilots need sufficient air to operate and 

large objects should not be placed in front or on the top of 

the broiler, which would obstruct the airflow though, the 

front of the broiler . 

For your safety NEVER place any type of object on top of 

the salamander broiler or cheese meters . The top of the 

broiler will exceed 1000°F . It could cause severe burns or 

fire and obstruct ventilation . 

Testing And Adjustments

All fittings and pipe connections must be tested for leaks . 

Use approved gas leak detectors, soap solution or equivalent, 

checking over and around the fittings and pipe connections . 

DO NOT USE A FLAME! Accessibility to all gas lines and 

fittings require that valve panel(s), lower front panel(s) be 

removed . It may be necessary to remove or at least raise and 

secure top grates . All parts removed (including fasteners) 

should be stored safely for re-use .

Testing

1 .  Be sure all valves are in the “OFF” position

2 .  Turn on the main gas supply valve . Light all top section 

pilots .

3 .  Leak test all valves and fittings as described in the 

procedure above . Correct any leaks as required and 

recheck . 

4 .  Shut off all gas valves . 

All units are tested and adjusted at the factory . However, 

burners and pilots should be checked at installation and 

adjusted if necessary .

Summary of Contents for MSR16

Page 1: ...Ontario L4W 1X4 CANADA Phone 905 624 0260 Fax 905 624 5669 Enodis UK LTD Swallowfield Way Hayes Middlesex UB3 1DQ ENGLAND Telephone 081 561 0433 Fax 081 848 0041 Part 1382684 01 08 2005 Garland Commer...

Page 2: ...expose you to airborne particles of glass wool ceramic fibers Inhalation of airborne particles of glass wool ceramic fibers is known to the state of California to cause cancer Operation of this produ...

Page 3: ...ry Regulations 6 Gas Supply 7 Ventilation and Air Supply 7 Testing And Adjustments 7 OPERATION 8 M MS Models 8 Pilot Lighting Instructions 8 Main Burner Operation 8 Shut Down 8 MST Models 8 Operating...

Page 4: ...Natural 6 WC 15mbar Propane 11 WC 28mbar For instillations in non combustible locations only NOTE Data applies only to North America Gas input ratings shown here are for installations up to 2 000 ft...

Page 5: ...re and maintenance Periodic inspections by your dealer or a qualified service company are recommended to check temperatures burner adjustments and ensure moving parts are operative Wherever possible a...

Page 6: ...salamander with sheet metal screws previously removed Wall Mounted Salamanders 1 Each gas appliance must be located with respect to building construction and other equipment so as to permit access to...

Page 7: ...stem to work properly replacement air must enter the room in which the vent is located The amount of air that is exhausted must equal the amount entering make up air INSTALLATION continued All gas bur...

Page 8: ...m pilot flame length should be required Too high a setting will cause the flame to lift off or will create excessive carboning Do not adjust the pilot flame lower than 7 8 22mm long because this can c...

Page 9: ...e point where the burner rods no longer glow and the flame travels back and forth on the face of the ceramics OPERATION continued This adjustment has been factory pre set however with changing pressur...

Page 10: ...otice that the valves are becoming harder to turn it is then time to have them greased We suggest an authorized service agent who is familiar with the appliance and working with natural and propane ga...

Page 11: ...depending on the installation Servicing must be carried out by competent persons in accordance with the law SAFETY It is essential that the instructions in this booklet are strictly followed for the...

Page 12: ......

Reviews: