13–8–612 Page 9
Minimum Air Flow* For Compressor
And Cooling (Cubic Feet/Minute)
Air Cooled
All Models
3000 cfm
* 80
_
F Inlet Air
FIGURE 2–2
FOUNDATION – The Electra–Screw
R
compressor re-
quires no special foundation, but should be mounted on
a smooth, solid surface. Whenever possible install the
unit near level. Temporary installation may be made at
a maximum 10
_
angle lengthwise or 10
o
sidewise.
Mounting bolts are not normally required. However,
installation conditions such as piping rigidity, angle of
tilt, or danger of shifting from outside vibration or mov-
ing vehicles may require the use of mounting bolts and
shims to provide uniform support for the base. Belt
alignment and tension should be checked after installa-
tion. (For information on belt alignment and tension,
see page 31.)
OIL RESERVOIR DRAIN – The oil drain is piped from
the bottom of the reservoir to the side of the frame. This
drain is approximately 2 inches above the floor level. If
this is not sufficient to conveniently drain the oil some
other methods of providing drain are:
1.
Elevate the compressor unit on a suitable struc-
ture to obtain the desired drain height.
If the compressor unit base is raised
above floor level, the space between
the floor and the base bottom must be
closed with solid material all around
to prevent recirculation of hot air from
the oil cooler end and over tempera-
ture operation.
2.
Construct an oil sump or trough below the floor
level and pump or bail the drained oil.
3.
Pump oil from the reservoir filler opening or drain
to a container.
ENCLOSURE – The compressor, electric motor, oil
cooler and aftercooler are mounted inside the enclo-
sure.
Service panels are provided for maintenance access.
Be sure to allow enough space around the unit for the
doors to be removed.
Any of the enclosure panels may be removed by open-
ing the latch and lifting it up slightly.
FIGURE 2–3 – COLD WEATHER INSTALLATION
Summary of Contents for EBB BB-7.5 HP
Page 12: ...13 8 612 Page 2 FIGURE 1 2 PACKAGE COMPRESSOR MOTOR SIDE FIGURE 1 3 PACKAGE BELT GUARD SIDE...
Page 13: ...13 8 612 Page 3 FIGURE 1 4 PACKAGE CONTROLLER END...
Page 16: ...13 8 612 Page 6 DECALS 206EAQ077 212EAQ077 218EAQ077 211EAQ077 207EAQ077...
Page 17: ...13 8 612 Page 7 DECALS 216EAQ077 217EAQ077 222EAQ077 221EAQ077 208EAQ077...
Page 32: ...13 8 612 Page 22 FIGURE 4 7 AUTO SENTRY S SOLID STATE CONTROL TOUCH PAD...
Page 33: ...13 8 612 Page 23 200EBB546 Ref Drawing FIGURE 4 8 WIRING DIAGRAM...
Page 53: ...13 8 612 Page 43 PIPING AND MOUNTING GROUP 213EBB810 B Ref Drawing...
Page 77: ...13 8 612 Page 67 INTEGRATED DRYER ASSEMBLY AND PIPING 301EBB810 A Ref Drawing...
Page 82: ...13 8 612 Page 72 300EBB541 B Ref Drawing...
Page 84: ......