FSP HySpirit series User Manual
16
http://www.fsp-group.com.tw/en/product/PVInverter.html
12.
Commissioning
Step 1: Check the following requirements before commissioning:
Ensure the inverter is firmly secured
Check if the open circuit DC voltage of PV module meets the requirement (Refer to Section
6)
Check if the voltage of the open circuit utility is approximately as same as the expected
nominal value from local utility company.
Check if connection of AC cable to grid (utility) is correct if the utility is required.
Fully connect to PV modules.
Check if AC circuit breaker (only applied when the utility is required), batter circuit breaker,
and DC circuit breaker are installed correctly.
Step 2: Switch on the circuit breaker of battery and then switch on PV DC breaker. After that, if
there is any connection with utility, please switch on the AC circuit breaker. At this moment, the
inverter is already turned on. However, there is no output generation from loads. Then:
If LCD lights up to display the status of current inverter, commissioning has been completed
successfully. After pressing “ON” button for 1 second when the utility is detected, this
inverter will start to supply power to the loads. If no utility exists, simply press “ON” button
for 3 seconds. Then, this inverter will start to supply power to the loads.
If an error occurs to this inverter, a warning/fault indicator will appear on LCD display. Please
inform your installer.
Step 3: Please insert CD into your computer and install monitoring software on your PC. Follow
the steps below to install the software.
1. Follow the on-screen instructions to install the software.
2. When your computer restarts, the monitoring software will appear as shortcut icon located in
the system tray, near the clock.
NOTE: If using modbus card as communication interface, please install bundled software. Check
local dealer for the details.