DEBRIS SEPARATING BAFFLE BOX (DSBB)

Installation Manual

English

PLAY SETUP VIDEO

Summary of Contents for Bioclean DEBRIS SEPARATING BAFFLE BOX

Page 1: ...DEBRIS SEPARATING BAFFLE BOX DSBB Installation Manual English PLAY SETUP VIDEO ...

Page 2: ...d with your product Please refer to these sheets for further details on the measurements of each main part along with specific measurements required to accurately assemble these components 2 Please Check your project drawings for the correct DSBB size This manual is for the large size DSBB with concrete walls Two people might be required for this installation Filter System Concrete Chamber Splitte...

Page 3: ...sembly Front Sliding Door Rail x1 Front Ramp Sub Assembly x1 Deflector Shields x2 3 8 X 1 5 SS Bolts Washers and Locknuts x14 3 8 x 2 25 Wedge Anchor Bolts Back Sliding Door Rail x1 1 4 SS Self Drilling Screws x1 Splitter Screen Sub Assembly x1 Right Cage Sub Assembly x1 Left Cage Sub Assembly x1 Sliding Door Sub Assembly x1 Skimmer Boom Cage ...

Page 4: ...ld up against the baffle wall Using a Marker mark a corner pre drilled hole located on top of the deflector shield Next Drill the anchor bolt hole using a Rotary Hammer with a 3 8 Drill Bit Careful not to drill through the wall After Drilling the Corner Anchor hole insert a 3 8 wedge anchor bolt Using a Power Drill with a 9 16 Socket fully tighten the anchor bolt to fully secure the Deflector Shie...

Page 5: ... Steps for remaning Anchor Bolts While maintaining the Deflector Shield leveled drill a hole on the opposite corner After Drilling the Corner Anchor hole insert a 3 8 wedge anchor bolt Using a Power Drill with a 9 16 Socket fully tighten the anchor bolt to fully secure the Deflector Shield Continue drilling a hole on the opposite side and inserting the wedge anchor bolt on the opposite side one ho...

Page 6: ...olts Fully tighten the anchor bolts using a Power Drill with a 9 16 Socket Begin step 2 by placing the Skimmer Boom Cage up against the back Baffle Wall Look at your project drawings to see how far down to place the Cage Locate the anchor bolt holes and drill the holes using a Rotary Hammer Drill with a 3 8 Dia Drill bit 2 Repeat and install the Second Deflector Shield Repeat the previous steps an...

Page 7: ...e 3 8 wedge anchor bolts and fully tighten the anchor bolts using a Power Drill with a 9 16 Socket Begin step 3 by placing the Left Cage assembly on top of both baffle walls and up against the back baffle wall The left cage should be placed on the Left side of the vault with the Louvers facing back towards the outflow Pipe 2 Securing the Cage to Both Bottom Baffle Walls Locate the Wall Mount in th...

Page 8: ...ottom Anchor Bolts There are two mounting plates located on the bottom of the cage Mark the hole locations on the slots located on the mounts and using a Rotary Hammer Drill with a 3 8 Drill Bit drill the anchor bolt holes Next Insert the 3 8 Wedge anchor bolts and fully tighten the anchor bolts using a Power Drill with a 9 16 Socket 4 Installing the Right Cage Sub Assembly Finally place the Right...

Page 9: ...anchor bolt holes After drilling the holes insert the provided 3 8 wedge anchor bolts and fully tighten the anchor bolts using a Power Drill with a 9 16 Socket Finally locate the four mounting legs located on the bottom of the Splitter Screen two on each side Drill the anchor bolt holes using a Rotary Hammer Drill with a 3 8 Drill Bit After drilling the holes insert the provided 3 8 wedge anchor b...

Page 10: ...d right ramps Begin step 5 by attaching the Top Ramps to the Cages Place one ramp at a time on top of the cages Secure the top Ramps using the provided self tapping screws Insert the screws through the ramps and into the cages Fully tighten the screws using a Impact Wrench with a 3 8 Socket Locate the bottom Left and Right Ramp Louver Place these ramps underneath the assembly one on the left and o...

Page 11: ...ack Sliding Door Rail on top of the Cages right next to the back Baffle Wall There are slots located on the back rail and on the Top of the Cages Make sure to match both the left and right slots Locate the drilled holes on the bottom ramps Push the louver ramp flush with the baffle wall Drill the anchor bolt holes using a Rotary Hammer Drill with a 3 8 Drill Bit Secure the Sliding Back Rail to the...

Page 12: ...ing Door Rail 4 Place the front Sliding Door Rail infront of both Sliding Doors right on top of the Splitter Screen Make sure to place the Sliding Doors inside the Door Rail Push the Door Rail in place and make sure to match the slots located on top of both the left and right cage Fully tighten the Front Sliding Door Rail 5 Using two 3 8 Bolts one per slot secure the Front Rail to the Cages Secure...

Page 13: ...Technical support 855 566 3938 stormwater forterrabp com Bio Clean Corporate Office 5796 Armada Drive Suite 250 Carlsbad CA 92008 https biocleanenvironmental com BioClean 2020 All Rights Reserved ...