4   Operational Recommendations

4.1    Do not start up the equipment dry. Vent air from the casing of    

the pump and the seal chamber before startup.

4.2    If soap was used to ease seal installation, flush the seal chamber  

with water before startup to prevent rotating face gasket O-ring  

slippage and subsequent loss of seal drive.

4.3  Adjust the barrier water flow rate so there is no more than a  

11°C (20°F) temperature rise between inlet and outlet temperature. 

The barrier outlet water temperature should never exceed 51°C 

(120°F). Consult Flowserve if you have any questions.

4.4    If the seal runs hot, above 51°C (120°F) or squeals, shut down the   

pump immediately as not to damage the seal. Check to see if the    

barrier water supply is working properly. If barrier water system is    

working correctly, check the seal housing dimension to ensure the  

seal is not over-compressed due to axial dimensional stack up  

problems. 

For special problems encountered during installation, contact your 

nearest Flowserve Sales and Service Representative or Authorized 

Distributor.

seal

end view

Suggested Barrier Water Supply System - Plan 53A                  

Figure 2

drain, normally closed

cooling out

pressure indicator (low)

pressure source,

normally open

outlet

inlet

pressure switch (high)

level switch (high)
   level indicator
level switch (low)

cooling in

Reservoir

liquid fill

normally closed

cooling coils

Summary of Contents for Durametallic Double CRO

Page 1: ...Installation Instructions Experience In Motion Durametallic Double CRO Dual single coil spring friction drive for applications with water lubrication properties...

Page 2: ...worn components Clean all piping plans 1 4 Check requirements for shaft sleeve and seal housing See Figure 1 To first obstruction Face of seal housing to be square to the axis of the shaft to within...

Page 3: ...ring in the gland cavity Press the stationary face into the gland with the sealing face orientated toward the inboard side of the gland Use hand pressure only Position the gland over the shaft or slee...

Page 4: ...only be torqued to establish a leak tight seal at the gland gasket Proper land bolt adjustment is especially important with clamp style inserts where torque may damage the insert In this case gland st...

Page 5: ...nd with the stationary sealing face orientated toward the inboard side of the gland Use hand pressure only Wipe the sealing face clean with alcohol 3 6 Position the gland over the shaft or sleeve with...

Page 6: ...e seal runs hot above 51 C 120 F or squeals shut down the pump immediately as not to damage the seal Check to see if the barrier water supply is working properly If barrier water system is working cor...

Page 7: ...ting Faces Spring Rotating Face Gasket O rings Gland Gaskets Stationary Faces Stationary Face Seat Gasket O rings gland gasket gland seat gasket O ring stationary face rotating face rotating face gask...

Page 8: ...rain its employees and contractors in the safe use of Flowserve products in connection with the specific application While the information and specifications contained in this literature are believed...

Reviews: