Lady Kitchener AG08 Dryback 

6.   FREESTANDING FLUE SYSTEM 

       INSTALLATION INSTRUCTIONS 

 
1.    Position heater on floor protector ensuring all heater  
       clearances are correct as per clearances on page 5. 
2.    Once the location is confirmed, the appliance and floor 
       protector shall be fixed to the floor itself (refer to   
       page 6 & 7). 
3.    Extend a plumb line from the centre of the fire flue pipe  
       spigot to the ceiling.  Mark position on ceiling and roof. 
4.    Trim hole and nog as required ensuring that a 25mm  
       safe clearance between combustible materials and flue 
       components is maintained.  Fix with non combustible  
       spacers and screws or clouts on all four sides. 
5.    Cut and frame (when required) an opening in the roof, 
       position the outer casing through the roof until it is flush 
       with the under side of the ceiling, making sure as with  
       the ceiling there is a 25mm safe clearance between  
       non-combustible materials and the flue components.  
       Fix as in step 4. 
6.    Fix appropriate flashing around outer casing to the  
       roof to ensure a weatherproof seal. 
7.    Assemble flue pipe sections ensuring all seams are in  
       line, the assembly is straight and crimped.  Ends are  
       pointing downwards.  Fix each joint with three stainless  
       rivets or self-tapping screws. 
8.    Place ceiling plate with folded edges upwards over  
       heater spigot. 
9.    Position the flue pipe into the heater spigot.  The flue  
       pipe can either lowered from the top as a single unit or  
       fed up from the room a length at a time, ensuring that  
       all joints are fixed properly. 
10.  Slide the inner casing into place, between the outer casing  
       and the flue pipe. 
11.  The flue pipe must extend 200mm above the outer casing. 
       Note:  Extra lengths of flue pipe, inner and outer casing 
      may be required to achieve the minimum clearance from  
      the roof. 
12.  Slide top spreader over flue pipe down into outer and inner  
      casing and tighten. 
13.  Slide cowl over flue pipe until it rests on spreader.  Secure 
      with rivets or self-tapping screws. 
14.  Fit rainhat.  Do not fasten as it must be removable for flue  
      pipe cleaning. 
15.  Fix ceiling plate to ceiling maintaining an even gap all  
      around flue pipe. 
      Note:  Ensure ceiling plate is spaced off from the ceiling with ceramic spacers supplied. 

 

A flue pipe shield must be fitted – see item 11 on page 6. 

 

CAUTION

:  Mixing of appliance or flue system components from different sources or modifying the 

dimensional specifications of components may result in hazardous conditions.  Where such action is 
considered the manufacturer should be consulted in the first instance. 

Summary of Contents for Lady Kitchener AG 08 DRYBACK

Page 1: ...All installations must be in accordance with these instructions Consult with the building authority having jurisdiction to determine the need for a permit prior to commencing the installation Failure...

Page 2: ...arnings 4 2 Installation Responsibilities 4 3 Floor Protector Requirements 5 4 Installation Clearances 6 5 Assembly Instructions 7 Fitting Seismic Restraints 8 6 Flue Installation 9 Minimum Height of...

Page 3: ...LAMMABLE LIQUIDS OR AEROSOLS IN THE VICINITY OF THIS APPLIANCE WHEN IT IS OPERATING Use caution when reloading with fuel Do NOT attempt to load fuel into the heater when the fire inside the stove is a...

Page 4: ...from these installation instructions or any doubt about them must be checked against the requirements of the Standards Please leave this manual with the owner when installation is complete 3 FLOOR PR...

Page 5: ...PTH FOR PED OR D BASE 554 470 444 412 389 360 334 306 F P DEPTH FOR LEG BASE 300 300 300 300 300 300 300 300 4 INSTALLATION CLEARANCES When installing the Lady Kitchener AG on a leg base ADD 70mm to v...

Page 6: ...ructions 6 Secure both fire and floor protector to floor see Seismic Restraint page 7 This is a New Zealand Standard requirement due to NZ being earthquake prone 7 Assemble and fit flue as per instruc...

Page 7: ...SE MODELS 1 Remove bolts at rear of fire box 2 Fit Seismic Restraint brackets 3 Secure both the floor protector and the appliance to the floor LEG MODELS 1 Place firebox on leg assembly and fit bracke...

Page 8: ...ards Fix each joint with three stainless rivets or self tapping screws 8 Place ceiling plate with folded edges upwards over heater spigot 9 Position the flue pipe into the heater spigot The flue pipe...

Page 9: ...Lady Kitchener AG08 Dryback 9 WARNING The appliance and flue system shall be installed in accordance with AS NZS 2918 2001 and the appropriate requirements of the relevant building code or codes...

Page 10: ...Lady Kitchener AG08 Dryback 10 LADY KITCHENER AG08 DRY IMPORTANT UPON INSTALLATION CHECK THAT THE TRIANGULAR BRICKS ON TOP OF THE BAFFLES ARE PLACED AS SHOWN B A F F L E S...

Page 11: ...ons Limited Manufacturers of Lady Kitchener Bronte Contessa Royale Zealandia Encore Coaster Athena Forte Deco Plaza Aqualux Kompact 98 Niven Street Onekawa PO Box 3231 Napier 4142 Phone 06 8438260 Fax...