Version: August 2020
10
Step 4: Install flue and connect to appliance
•
Flue installation must meet the requirements of AS/NZS 5601.1:2013 and comply with all local council
requirements and be installed and certified by a suitably qualified person.
•
Refer to appropriate ‘The Fire Dept’ product specifications for specific minimum requirements. Only follow
the
‘
Wall cowl assembly
details’
in this guide if the flue is to be terminated through a wall.
•
A 25mm clearance from combustible materials, 75mm clearance from wiring and plastic pipes and a
minimum of 5mm from non-combustible materials is required when installing a flue system for any appliance
supplied by
‘The Fire Dept.’.
•
The flue installation requires a restriction free cavity from the top of the firebox (flue spigot) to the outside
atmosphere.
•
Air flow must be unobstructed from the firebox to the inner flue and from the heat shield to outer casing
allowing air to circulate from the firebox to the flue casings to the atmosphere.
In-Line Fan assembly details
Step 1:
Step 1:
Connect the flue and outer casing to the firebox
1. Make sure the In-line fan has adequate access for future maintenance.
2. Run the flue from the appliance to the location of the In-line fan.
3. Run the outer casing from the appliance to finish 50mm shorter than the flue.
Step 2:
Connect the in-line fan to the flue and outer casing
1. Fit the flue over the inlet spigot to the In-line fan.
2. Fix the flue to the inlet spigot at the in-line fan.
Step 3
Complete the flue installation
1. Finish the casing with a 50mm gap to the in-line fan.
2. Compl
ete the flue installation .Refer to appropriate’ product specification for
fixing details and specific minimum requirements.
Flow from In-Line
Fan to termination
Flow from firebox
to In-Line Fan