Doc# 71-0170
4215-141
Rev. 02
9
08/23/2022
Temp Sensor Installation
33.
Locate predrilled hole in the front ceiling panel. It will be in the
front right corner. Feed the temp sensor cable through the hole
with 3-4 inches of cable exposed.
(Image 18)
34.
Connect cable to the back of the sensor board.
35.
Secure the sensor board to the ceiling.
36.
Place the cover over the temperature sensor board.
37.
Remaining sensor cable should be routed to the CB box. See
heater installation manual for details
Heater Guard Installation
38.
Place the heater guard around the heater as described in your
heater instructions. Spacing may vary according to heater kilowatt.
Electrical / Heater Assembly
39.
A licensed electrician should wire the heater. Defer to heater
installation manual for directions.
*Rocks will be placed after testing the heater.
*See Himalaya manual for heater installation.
NOTE: One of the wall panels has a removable board to allow for
wiring access to the heater (Image AA). This tongue and groove
board located in the trim package. Do not install until after the
wiring is completed.
(Image 20)
Once electrical is connected test SL2 control and lighting
A qualified electrician should complete all electrical connections.
Complete the following steps after electrical connection has been
established.
40.
Press the room light button to ensure backrest lights turn on.
41.
Press the ON button and allow heater to run for 15 seconds, then
turn off.
42.
Put your hands close to the elements (DO NOT TOUCH) to feel if all
three elements are heating, or have the electrician verify the
correct Amp draw for your heater.
Image 18
Image 20
Image 21
Image 19