Commissioning
Installation 1
st
Stage
The Power Supply Unit back box should be mounted, with the mains supply tested, connected and isolated
at the un-switched fused spur, ready for the commissioning engineer.
The installer needs to provide a set of
As-Wired
drawings and proof of
cable continuity and insulation
test readings
etc., to enable commissioning to proceed. This information is essential for commissioning
and programming to proceed, and may be entered onto the forms provided at the rear of the manual.
Power Up
It is generally advisable that this Power Supply Unit should be powered up by making the 230V AC mains
connection before the batteries are connected.