Prepare the guide bracket, as follows:
- use a “U” profile with dimensions indicated in fig. 9;

b) existing gate with adjustable hinges

- Remove the bottom hinge.
- Slacken off the top hinge.
- Swing the leaf around the axis of the top hinge (fig. 4).

c) New gate to be installed

- Fit just the top hinge. If possible use an adjustable

hinge.

1)

Dig out a hole for the foundation box as shown in fig. 5.

Fig. 4

65

156

S

58

Fig. 5

Fig. 6 a

Fig. 6 b

=

=

~ 440

~ 315

90 °

Fig. 7

N.B.:

 Depending on the nature of the ground, it may be

necessary to cast a bed of quick-setting concrete at
the bottom of the hole to avoid subsidence in future.

2)

Place the foundation box in the hole, respecting the
dimensions given in fig. 6/a-b.
The center of the pivot on the foundation box must be
perfectly aligned with the leaf’s axis of swing (fig 6/a-b).

3)

Lay down a PVC tube of diameter 35 mm through
which to pass a 4 core electrical cable. The tube must
reach from the box the control unit (fig. 7).

Lay a second tube to drain off rain water, from the box
to the nearest drain (fig. 7).

4)

Fix the box in place with a casting of concrete.

3.3

SETTING UP THE GATE

Note: 

Wait for the cement to set before starting this

operation.

1)

Assemble the release levers on the support bracket,
and fit the latter on the pivot in the foundation box, also
inserting the ball supplied (fig. 8).

Note: 

Grease both the pivot and the ball.