Summary of Contents for 116351

Page 1: ...J355HA M50 www FastGateOpeners com 800 878 7829 Sales FastGateOpeners com ...

Page 2: ...s currently in force 10 Beforeperforminganyoperationonthesystem disconnectthepowersupply 11 The power mains of the automation system must be fitted with a multi pole power switch with a switch contact gap of at least 3 mm It is advisable to use a 6A circuit breaker with a multi pole power switch 12 Ensure there is a residual current device with a 0 03 A threshold upstream of the system 13 Checktha...

Page 3: ...ards The cylinder is moved by a hydraulic unit inside the structure 1 2 TECHNICAL DESCRIPTIONS AND SPECIFICATIONS 1 Flashing LED 2 Head 3 Cylinder 4 High position magnetic contact N C 5 Junction box 6 4 stops devices upper position 7 Oil filler plug with dipstick 8 Hydraulic control unit 9 Lowering solenoid valve 10 Cable guides 11 EFO accumulator 12 Pressure switch 13 EFO solenoid 14 Ø 100 mm hol...

Page 4: ...re C 15 55 Weight of bollard and pit kg 850 bollard 235 pit Oil quantity l 1 6 standard version 6 7 EFO version Ingress protection IP66 Size See 2 Condenser 2 70μF 400V Resistance to breakage J 3 1852000 1 Check the oil level using the dipstick positioned under the filler cap 1 7 with the piston rod fully inside and the EFO system under pressure 2 The starting capacitor 70μF 400v is pre wired insi...

Page 5: ...STALLATION 2 1 CONFIGURATION A flexible hose with a diameter of Ø100 mm should be fitted for drainage Dig the hole to a depth of approximately 1 85 m Dimensions in mm UNPROTECTED AREA IMPACT DIRECTION PROTECTED AREA Ground Excavation www FastGateOpeners com 800 878 7829 Sales FastGateOpeners com ...

Page 6: ...nstructions ENGLISH 2 2 CONSTRUCTION OF THE FOUNDATION CAGE Build the foundation cage not supplied by FAAC as shown in 4 using the Ø 12mm and Ø 20 mm iron rods CLASS B450C www FastGateOpeners com 800 878 7829 Sales FastGateOpeners com ...

Page 7: ... electronic board 7 Pour class C30 37 concrete around the cage to secure it properly up to about 10 cm from ground level Wait a minimum of 7 days to allow the concrete to cure properly Laythepipingnecessaryforconnectingthebollard thecontrolboard and any additional devices and finish the road surface with the same type of concrete N B All piping must be laid in compliance with the applicable rules ...

Page 8: ... 30 pursuant to UNI EN 12620 The bollard must only be installed once the concrete has cured for at least 7 days The compaction index of the surrounding soil should be at least 90 of the optimal Proctor curve pursuant to the UNI EN 13286 2 2005 standard The steel reinforcement complies with the B450C class ASTM A615 Grade 60 Whilst the concrete is curing insert one or more of contrast supports insi...

Page 9: ...andpassedthrough the cable guides provided on the pit sheet 8 1 and through the two corrugated conduits supplied with the pit Pass the wires through on the guides on the bollard frame as per as 8 2 then connect the corrugated conduits to the supports on the bollard frame as indicated in 8 3 Complete the electrical connections in the terminal box at the side of the bollard as shown in 14 Any additi...

Page 10: ...rd resting it against the coun terframe remove the two eye bolts 11 1 and fix the bollard in place using the 24 TCEI M24x50 screws supplied with the pit IMPORTANT Tighten the screws to a torque of 50Nm 2 6 FIXING THE TOP COVER Afterfixingthebollardinplace completetheinstallationbyposition ingandfixingthetopcoverwiththesixM8x40steelscrewsprovided Screw the two male M20 eye bolts onto the upper part...

Page 11: ...crewandremovethefourTORXT30screwssecuringthecover of the hydraulic control unit in place 13 1 4 Remove the cover of the hydraulic control unit 5 Unscrewthelocknut 13 2andloosenthescrew 13 3tomove the cylinder downwards 2 9 AUTOMATIC OPERATION To restore automatic operation 1 Turn the screw 13 4 until the stop point in order to restore automatic operation 2 Tighten the lock nut 13 5 3 Repositionthe...

Page 12: ... pressure switch EFO solenoid valve Heater optional Refer to the diagram below EFO N O connection activtes also in case of black out EFO N C connection voluntary activation only Before performing any work on the electronic equipment connections maintenance always turn the power off Install a differential thermal breaker upstream with adequate tripping threshold 0 03A Connect the ground cable to th...

Page 13: ... Y 7 PresstheFbuttonandholditdownwhilstsimultaneouslypressing the button to exit programming screen and save the changes made For more information on programming the equipment please refer to the relevant instructions 3 3 TROUBLESHOOTING Below are a series of tips to help identify and solve a number of particular issues CONDITION SUGGESTION The bollard will not rise it remains in the low position ...

Page 14: ... STOP LOOP 1 LOOP 2 LOOP 2 LOOP 1 CLOSE FSW EMERGENCY OUT 1 OUT 2 OUT 3 GND GND 24 V 24 V OUT 3 3 7 11 13 1 dF 06 LO C 3 03 Y 4 LO Cu F F F F F F F F F F 10 s F F 10 s Translation of the original instructions ENGLISH 3 4 CONNECTING SEVERAL BOLLARDS MASTER SLAVE Youcanoperatemorethanonebollardsimultaneously andthesecanbeinterconnectedusingthecorrespondingJE275deviceintheMASTER SLAVE configuration F...