For more information call 1-800-654-8168 or go to www.ez-dock.com.
10
Step 3:
Assemble a Full Bow Section at the front of the EZ Port MAX Extension. (See page 8, Figure 2 for Full Bow Section
assembly instructions).
Step 4:
The half bow section (206025BS-xx) is required for use between PWC’s. The half bow section is assembled at
the front of the entry section as a removable stop between the PWC’s (refer to Page 8, Figure 1). The half bow section is
tethered using a nylon tether (Item 3) and two (2) bolts (Item 2). When used on an in-line port application Item 2 and Item 3
are required and the four (4) bolts (Item 4) are omitted.
Step 5: Installation -
For Installation/Attachment of the assembled in-line EZ Port MAX Entry + Extension please see below
and refer to the Installation/Attachment Section, pages 8 - 18.
Hinge kit (see Section 5, 6) used to anchor to a floating dock. Add hinge kit to entry section if additional stability is required.
Additional hinge, 100751
or 100751SS if required.
Floating Dock
When anchoring the Port MAX in the in-line configuration with pipe (Section 1.), only use the integrated pipe bracket locations at
the front of the EZ Port Extension. If additional stability is required, a pipe bracket(s) may be added to the outside of the entry
section.
Do not use pipe here with in-line configuration.
Additional pipe bracket (s), 130251 on ouside of port.