Installation
17
Feed both pellet hoses to the boiler and attach to the
connections with hose clamps. Remove the earthing
wires from both pellet hoses and connect to the earth
terminal on the boiler.
Fig. 4-19: Connections on the boiler (e.g., ePE-K)
Fig. 4-20: Connecting the copper wire to the earth
Securing the connection box
Attach the junction box near the filling pipes in a
protected but easily accessible place. The mounting
height should be about 1.5 - 1.8 m for comfortable
operation.
Fig. 4-21: Connection box
For the power supply of the junction box, a 230 V outlet
in the immediate vicinity is required. The connection
cable is included in delivery.
Leading the cables to the connection box
Connect the electric cable with the preassembled plug
to the lifting module. Feed this cable in the pellet store
in a closed installation tube to the wall bracket and
from there through the PG screw joints to the
connection box.
Fig. 4-22: Connecting the cable to the lifting module
Lead the electric wire from the mole as well and
through the PG screw connection to the connection
box. The electrical connection is described in chapter
.
Fig. 4-23: Leading the cables to the connection box
Mounting the opposite cover plate
Fill the opening in the wall with rock wool. This
minimizes the transmission of noise into the wall and
also provides the required fire safety. Slide the cover
plate against the wall and check that it is level. For an
Summary of Contents for Mole E3
Page 19: ...Installation 19 ...
Page 32: ...www eta co at www eta co at downloads DOWNLOAD ...