Upper & Lower Belt Tracker
7
14/06/2021
SECTION 3 - PREPARATION FOR INSTALLATION
1. CHECK INSTALLATION DRAWINGS
– Ensure that you have the correct drawings and
equipment for your conveyor/s.
2. PRE-ASSEMBLE THE BELT TRACKERS AND MOUNTS
– Do this in your workshop or
similar area, rather than at the conveyor. This will enable you to:
(a) Verify all required equipment is present.
(b) Familiarise yourself with the Belt Tracker assembly.
(c) Allow you to plan the installation, reducing installation time.
3. ASSEMBLE THE FOLLOWING TOOLS;
-
Wrenches (for M16, M10, M12 Bolts)
-
Adjustable Wrenches (300mm) x 2
-
Metric/ Imperial Allen Keys
-
Measuring Tape and Steel Rule
-
Electric Drill & Grinder (if allowable)
-
Welding and Cutting Equipment
-
G-Cramps
-
Square, Level, Straight Edge
-
Chalk or Marker
-
Lead Lights, Flash Light
-
Safety Equipment
-
Scaffolding as required