M O T U S N F R V › I N S T A L L A T I O N G U I D E
|
D O O R L E A F I N S TA L L AT I O N
1 7
4a
The bracket fits onto the bolt as shown.
4b
Feed the rest of the door at least halfway
into the pocket and hang the front bracket
onto the trolley bolt.
4c
With spanners provided, wind the bolts up
or down to plumb the leading edge of the door
and to achieve the required gap under the
door (door undercut).
Tighten the locking nuts to secure the door to
the brackets. They may need to be slacked-off
later, to true the door to the trims once they
are fitted.
HANG THE DOOR
4
4b
4c
Adjust the bolts to achieve a gap
approximately
15mm
between the underside
of the track and the top of the bolt.
ASSEMBLE GEAR
4a
3
The door leaf needs to be hung before the trim is fitted.
FIT THE GUIDE CHANNEL
200mm
150mm
100mm
Apply a thin bead of adhesive into the groove in
the bottom of the door and then tap the plastic
channel into position.
Double Doors
Fit brackets
100mm from the back
edge and
200mm from the front
so the two
doors meet in the centre over the 100mm sync unit. (Instead of hanging equally as per the singles.)
Single Door
Position the brackets equally to the edges of the door, spaced to
150mm
centres.
SINGLE
DOUBLE
1
2
FIT HEAD BRACKETS
150mm
Door leaf installation