3 – 2
VSG/VSSG • Installation, Operation and Maintenance Manual •Vilter/Emerson • 35391STG
line valves and run the oil pump for 10 seconds prior
to rotating the compressor shaft. Continue running
the oil pump while the compressor shaft is being
turned to help lubricate the surfaces of the shaft seal.
For cool compression, there is no pre-lube pump, so
the driveshaft must be turned by hand.
• Maintenance log to be kept with documenting dates
to show all the procedures have been completed.
• Notify Vilter Service and Warranty Department when
the compressor is started.
COMPRESSOR MOTOR
The following are general recommendations. Refer to
speci
fi
c motor manufacturer instructions for storage
recommendations.
• Cover the motor completely to exclude dirt, dust,
moisture, and other foreign materials.
• If the motor can be moved, it is suggested that the
entire motor be encased in a strong, transparent plas-
tic bag. Before sealing this bag, a moisture indicator
should be attached to the side of the motor and sev-
eral bags of silica-gel desiccant be placed inside the
bag around the motor. When the moisture indicator
shows that the desiccant has lost its effectiveness, as
by a change in color, replace desiccants.
• If equipped, space heaters must be installed to
keep the motor at least 10°F above the ambient
temperature.
• Add grease every 3 months.
• Cover all bare metal surfaces with rust inhibitor.
• Manually rotate motor shaft several revolutions (ap-
proximately 6) every 3 months to prevent
fl
at spots
on the bearing surfaces.
Long Term Storage Recommendations
The procedure described is a general recommendation
for long term storage (over one month of no operation)
of Vilter compressor units. It is the responsibility of the
installation
fi
rm and end user to address any unusual
conditions. Use the supplied long term storage log sheet
to help with record keeping, see section page 3-4.
Warranty of the system remains in effect as described at
the beginning of this manual, section page i.
The following are recommendations regarding long
term storage:
• If the unit is designed for indoor duty, it must be
stored in a heated building.
• If the unit is designed for outdoor duty and is to be
stored outdoors, a canvas tarp is recommended
for protection until installation. Adequate drainage
should be provided. Place wood blocks under the
base skid so that water does not collect inside the
base perimeter or low spots in the tarp.
• All compressor stop valves are to be closed to isolate
the compressor from the remainder of the system.
All other valves, except those venting to atmosphere,
are to be open. The unit is shipped with dry nitrogen
holding charge of approximately 5 psi above atmo-
spheric pressure. It is essential that the nitrogen hold-
ing charge be maintained.
• Cover all bare metal surfaces (coupling,
fl
ange faces,
etc.) with rust inhibitor.
• Desiccant is to be placed in the control panel. If the
panel is equipped with a space heater, it is to be ener-
gized. Use an approved electrical spray-on corrosion
inhibitor for panel components (relays, switches,
etc.)
• All pneumatic controllers and valves (Fisher, Taylor,
etc.) are to be covered with plastic bags and sealed
with desiccant bags inside.
• The nitrogen or clean dry gas holding charge in the
system and compressor are to be monitored on a
regular basis for leakage. If not already installed, it is
required that a gauge is to be added to help moni-
tor the nitrogen holding charge pressure. If a drop in
pressure occurs, the source of leakage must be found
and corrected. The system must be evacuated and
recharged with dry nitrogen to maintain the package
integrity.
• Manually rotate compressor shaft several revolutions
(approximately 6) every 3 months to prevent
fl
at
spots on the bearing surfaces. If the compressor unit
is installed, wired and charged with oil, open all oil
Section 3 • Installation