5.2
3" through 24" PT Meter assembly
CAUTION
MECHANICAL EQUIPMENT DAMAGE
See Section 7 “INSPECTION” prior to assembly.
Failure to properly clean and inspect all parts according to Section 7 “INSPECTION” may
result in meter damage and improper operation.
Procedure
1. If rimmed rotor meter, install deflector ring by sliding it, widest edge first, into
upstream end of meter housing until contacting the step in the bore.
Note
Rimless rotor meters do not have a deflector ring.
Figure 5-17: Step 1
2. Insert angled end of hanger blades into the three slots in a hanger hub. When
correctly installed outside hanger blade edges are parallel to hanger hub. The
upstream and downstream edges are perpendicular to hanger hub.
Figure 5-18: Step 2
Installation and maintenance instructions
Disassembly and assembly instructions
3-9008-011
October 2019
Installation and maintenance instructions
47