26 Chapter 3 Electric Installation
Liebert.PEX Chilled Water Series Air Conditioner User Manual
Chapter 3 Electric Installation
This chapter introduces the electric installation of the chilled water AC, including the work introduction,
installation notes, wiring of the unit and installation inspection.
3.1 Work Introduction And Installation Notes
Wires to be connected on-site
1. Unit power cables.
2. Unit input and output control cables.
Installation notes
1. The connection of all power cables, control cables and ground cables must comply with local electrician
regulations;
2. See the equipment nameplate for the full load current. The cable sizes should meet the local wiring rules;
3. Mains supply requirement: 380Vac, 50Hz;
4. The electrical installation must be completed by trained personnel;
5. Before the wiring, use a multimeter to measure the power supply voltage and make sure that the power
supply has been switched off.
3.2 Wiring Of Chilled Water AC Unit
3.2.1 Locating Electrical Interfaces
Opening the front door of the chilled water AC unit can reveal the interfaces of electrical control box, as
shown in Figure 3-1, Figure 3-2 and Figure 3-3.
Control interface
N/PE terminal block
Power interface
Upflow
Power interface
Control interface
N/PE terminal block
Downflow