41
Maintenance
OPERATOR PROTECTION. Use safety equipment according to the company regulations.
Use this safety equipment within the work area during installation, service and when handling
chemicals:
• protective mask
• protective gloves
• safety goggles
• ear plugs or hear muffs
• further security device, if necessary.
POWER SUPPLY DISCONNECTION. Always disconnect main power before you perform any
installation or maintenance tasks. Failure to disconnect power will result in serious physical injury.
Installation and maintenance tasks should be carried out by AUTHORIZED AND QUALIFIED
PERSONNEL only in accordance with local regulations. LOUTUS AIR does not require any
particular maintenance except for the typical use of traditional dosing pumps. Therefore, it is
advisable to check the fittings and lances in the tanks to prevent leaks and, if necessary, to clean
or replace the suction, delivery and discharge pipes, paying attention to any leaks or residues.
In order to facilitate the cleaning and maintenance procedure of the LOTUS AIR, the “CLEAN”
menu is available (see relative paragraph). Always adopt all the individual and environmental
safety devices provided in the presence of dioxide. In this regard it is necessary to read carefully
the security chapters in this manual.
A maintenance schedule includes these types of inspections:
• Routine maintenance and inspections
• Three-month inspections
• Annual inspections
Routine maitenance and inspections
Perform these tasks whenever you perform routine maintenance:
• Ensure that there are no leaks from the orings.
• Check electrical wiring
• Check for unusual noise and vibration (noise allowed 70.4 dbA; ± 5 dB).
• Check the pump and piping for leaks.
• Check for corrosion on parts of the pump and / or on hoses.
Three-month inspections
Perform these tasks every three months:
• Check that the tightenings.
• Check the mechanical seal if the pump has been left idle.
• Check the correct operation of motorized valve (closing opening)
• Check the water inlet filter and the solenoid valve seal
• Check the reaction and storage level probes.
Annual inspections and replacements kit
Perform these inspections one time each year:
• Calibrate chlorine dosing pump
• Check the pump capacity (as per nameplate).
• Check the pump pressure (as per nameplate).
• Check the pump power (as per nameplate).
• Check electrovalve a water suction valve
• Replace pumps heads and carbon filter (ask for a replacement kit)