Pump Calibration
This function allows the calibration of the “chlorine dioxide” dosing pump based on strokes capability. To calibrate,
proceed as follows:
1. Set strokes of the metering pump according to its capability (eg 100)
2.
Place an additional suction hose in a graduated beaker
3. Move curson on Mode, press wheel, select Start, then press the knob.
4. Wait until the end of the 100 strokes
5. Measure the product in the Becker
6. Enter measured quantity in ml (ml field). The instrument calculates the cc/s that the pump is able to produce.
7. Move cursor on OK and press the wheel to save settings.
In the event of an emergency, procedure can be interrupted moving cursor on Mode and selecting STOP.