UM/SWHM/V3/0115   

 

 

 

 

              Fig. 3:  Connection diagram for CT Operated Three Phase Prepaid Energy Meter 

 

Wire the Dual Input 

The Unit is capable of monitoring electricity consumed from two separate sources. One of these could 

be the supply from the electricity authorities while the other could be from the in-house generator. For the 

meter  to  recognize  that  the  supply  is  from  the  alternate  source,  the  meter  requires  a  voltage  input 

between 240 V AC that should go live when the supply is from the alternate source as shown in Fig 2. 

Wire the Digital Inputs (Max.4) 

Integration  of Gas  and Water with  the  electrical  parameters thereby,  extending  the  flexibility  for  the 

user  to  budget  expenses.  The  four  digital  inputs,  any  gas  and  water  meter  can  be  configured.  It  is 

important to program the price / Pulse in the corresponding ElNet PPS. 

 

Wire the Communication (RS485)   

The Prepaid  Energy Meter  is  equipped  with  an  RS-485  Serial  Communication Port  or GSM/GPRS  and 

operates on the

 

MODBUS-RTU protocol. 

 

Wire the Remote Unit  

The  Prepaid  Energy  Meter  is  equipped  with  Remote Unit; it  has  four  terminals,  two  terminals  for  5V 

supply to Remote Unit and two terminals for RS485 communication to Remote Unit. 

 

2.3.

 

INSTALLING THE METER 

The  device  should  be  installed  in  a  place  where  it  will  not  be  at  risk  of  damage  or  near  any 

unauthorized current connection. The sealing of the distributor housing is recommended. The 

producer is not responsible for any damage caused by improper assembly, service and product 

maintenance. 

 

Summary of Contents for PE5120

Page 1: ...1 UM SWHM V3 0115 User Manual PREPAID METER THREE PHASE SINGLE PHASE www elmeasure com...

Page 2: ...REMOTE UNIT 11 3 PREPAID METER CONFIGURATION 12 3 1 PREPAID METER PRODUCT DESCRIPTION 12 Physical Description 12 Models Display parameters of Prepaid meter 14 3 2 PREPAID METER OPTIONS 14 4 PREPAID ME...

Page 3: ...ces also can integrate gas and water meter with the different inlets of the house and deduct the balance based on consumption The meters can be networked with RS485 GSM GPRS The unique data communicat...

Page 4: ...the meter with credit revenue through secured communication Elmeasure encryption is added on top of this to provide the better security Emergency credit for the selected customer Remote ON OFF load by...

Page 5: ...housing colonies As a second meter between utility meter and distribution board for housing tenants Selective deployment by utilities in regions with poor credit history Electricity supply for vendors...

Page 6: ...lied OPTIMUM FIELD CONDITIONS For the reliability and better life of the product the unit has to be operated at moderate temperatures and humidity The meter is designed to work from 5 to 60 degree C a...

Page 7: ...so is a good insulator Hence it DOES NOT HAVE ANY EARTH TERMINAL Terminal cover is to be used to protect the meter terminals from being tampered with As soon as the connections are made the terminal b...

Page 8: ...alue it is not advisable to leave a reversalofcurrentflowuncorrected It is important to adhere to phase relationships Current IR must correspond to the phase that has the Voltage connected to the VR t...

Page 9: ...r to budget expenses The four digital inputs any gas and water meter can be configured It is important to program the price Pulse in the corresponding ElNet PPS Wire the Communication RS485 The Prepai...

Page 10: ...eter mounting mechanism is same Turn off the line power to the existing meter Caution Test existing meter terminals to be sure the voltage is off Remove the line and load wires from the existing meter...

Page 11: ...k down symbol of the SIM holder Insert the SIM into the holder Lock the SIM holder by click up symbol of the SIM holder 2 3 4 INSTALLING THE REMOTE UNIT Connect the Remote unit power supply and RS485...

Page 12: ...the following indicators and controls 7 segment LED display One row of alphanumeric displays six digits each displays all parameters simultaneously For every second the display updated Indicators One...

Page 13: ...10 00 M and 1 0 M as 1000 K MINUS Minus When lit indicates that the reading is negative When PF power factor is lead capacitive load Both PF and VAR reactive power sign will be negative When current...

Page 14: ...tage Current Frequency Watts VA PF Cumulative kWh Cumulative kWh EB DG Credit left in kWh Units balance Digital Inputs for Gas and Water meters Cumulative Old KWh EB DG Digital Inputs old for Gas and...

Page 15: ...or DG Elmeasure meters have the unique feature to program the set limit for consumption when it is operating on EB and DG in terms of kVA When the consumption is above the set value then the LOAD get...

Page 16: ...t reset WiFi module If Y is selected meter enters in to wifi reset mode 4 3 PROGRAMMING GUIDE FOR 3PHASE PE5120 1PHASE PE5121 PREPAID METER Step Actions Display Reads Range Options Comments 1 Press UP...

Page 17: ...he Hour Minute Row 01 01 t Follow the procedure steps 8 9 for set the Hour minute 12 Press DOWN key to go to the next parameter Row 52 00 Eb Default in 3phase 17 50 Eb Default in single phase Over KVA...

Page 18: ...me method until fourth digit Program Range for Over Voltage 80V to 310V If value set is above this limit display returns to the maximum O V value acceptable 21 Press DOWN key to go to the next paramet...

Page 19: ...nt time during auto scroll A t 5 000 1 to 10 seconds Enabling and Disabling of Auto scrolling Enabling Auto Scrolling Press DOWN key continuously for 5 seconds or until display shows EnAb Au for downw...

Page 20: ...ost cost per KWh and the slab wise cost Remote Configuration of change in Threshold Negative balance Tariff in the secure mode Initiate the SMS when balance reaches the 20 or 15 of the threshold value...

Page 21: ...gator AG 1000 Aggregator AG1000 is a web based high end data concentrator and All In One multi protocol communication interfacing unit that supports the Modbus protocol and has different types of comm...

Page 22: ...wall mountable Communication channels available in AG1000 RS485 with Isolated wired Ethernet wired Wi Fi wireless Bluetooth Wireless Zigbee Wireless GPRS 2G 3G wireless 4 5 PREPAID FUNCTIONS Advanced...

Page 23: ...ergency Credit Limit defines the credit value which is available after the value of Available Credit Register reaches zero and the customer selects the emergency credit Emergency Credit Threshold defi...

Page 24: ...ys 2 programmable Weekend holidays can be programmed to any 2 days or 1day Happy Hours can be programmed to any time of the day Service provider can Force off and on the load Emergency credit to take...

Page 25: ...121 1650 for PE5120 Shipping packed 750 gms for PE5121 1750 for PE5120 Dimensions mm 160 112 mm Depth 58mm behind bezel The following table gives the Technical Specifications of the Prepaid Three phas...

Page 26: ...industrial applications The key features of RS 485 that make it ideal for use in industrial communications and the applications are Bi directional communication in the single pair of twisted cables Mu...

Page 27: ...tocol WAP as well as other wireless data services GPRS was one of the earliest cell phone data access technologies GPRS is the most widely supported packet data wireless technology in the world Like G...

Page 28: ...ge as many square kilometers achieved by using multiple overlapping access points Features and benefits of WI FI Enable staff to carry portable Wi Fi handsets giving them the ability to work anywhere...

Page 29: ...nd control of functions and instrumentation for Hydro graphic water supply reservoirs sewerage systems Electrical power transmission networks and associated equipment Natural gas networks and associat...

Page 30: ...loat 40161 33 Reserved communicates zero float 40161 34 Wh DG if meters is manufactured for Wh VAh DG if the meter is manufactured for VAh float 40167 8 TROUBLESHOOTING CAUTION During reparation and m...

Page 31: ...he RF card recharge properly Display blinking Balance is below the limit Load off condition Check the balance is zero Check the over voltage occur Check the over KVA occur If RS 485 communication does...