background image

 

 

Technical Support: +44(0)23 9269 6638 (option 3) 

  PAK200574_01K May  2016                       ©2016 ELMDENE INTERNATIONAL LTD  

 
Standby Battery 

10)

 

Select the Battery type by placing the link (above the Battery fuse) in the appropriate location to 
select (17/18 Ah, 38 Ah or 65 Ah) batteries. This changes the maximum bulk charge current, and 
therefore enables higher load current to be used when smaller batteries are required. Put the link 
on the left hand two pins for 17/18 Ah, the middle pins for 38 Ah and the right hand two pins for 65 
Ah batteries.  

 
 
 
 
 

Figure 6 – Standby battery size selection links

 

 
11)

 

Mount the appropriate batteries as shown above. Where a dual box solution is used all cabling 
between the two boxes should be routed to use separate case entry/exit holes from other cabling 
and use suitable bushes to protect the cables. 

12)

 

Connect the two 12 V standby batteries in series using the single cable provided. Connect the 

negative

 of one battery to the 

positive

 of the other. 

DO NOT CONNECT

 the other two battery 

terminals to each other. 

13)

 

Connect the free Positive and Negative terminals of the batteries to the PCB terminals Batt+ and 
Batt - using the cables provided. See Figures 4 & 5. 

14)

 

Connect the battery temperature sensor (two white wires) to the PCB terminals TMP Sens. See 
Figure 5. 

15)

 

If the batteries are housed remotely, replace the battery lead assembly (including battery 
temperature sensor) with an extended length assembly, provided with the Battery box (Ensure the 
temperature sensor and battery connections are made according to figure 5. 

16)

 

Re-apply the mains power and verify that the yellow Fault LED stops flashing after about 20 s 
(battery connection detected). Verify that the remote GEN PSU Fault monitor shows a 

closed

 

contact. 

17)

 

Disconnect the mains power. Verify that the green Mains LED extinguishes and the yellow Fault LED 
starts to pulse (indicating that the PSU is running from its standby batteries). 

18)

 

If connected, verify that the EPS Fault monitor shows an 

open

 contact and the PSU Fault monitor 

shows a 

closed

 contact. 

19)

 

Perform a full functional test of system including full alarm condition. Verify that the standby 
batteries can support the system load. Note: ensure batteries have sufficient charge. 

Final 

20)

 

Reconnect the mains. Verify that the green Mains LED illuminates and the yellow Fault LED 
extinguishes. 

21)

 

If connected, verify that the EPS Fault monitor shows a 

closed

 contact and the GEN PSU Fault 

monitor shows a 

closed

 contact. 

22)

 

Close cover and secure using fastening screws provided. 

 

 

17/ 18 Ah 

38 Ah 

65 Ah 

Summary of Contents for BATT-BOX-65

Page 1: ...volt free solid state relay fault output signal i loss of mains and ii battery fault charger fault and loss of output In addition there is an RS232 serial interface that can provide diagnostic and fau...

Page 2: ...A 7 5 A 10 0 A 7 2 A 6 5 A Battery Capacity eg PowerSonic model Yuasa model Interlogix model 2 x 17 18Ah 12 V PS12170 NP17 12 BS131N 2 x 38 Ah 12 V PS12380 NP38 12 2 x 65 Ah 12 V PS12650 NP65 12 BS13...

Page 3: ...N Fault Condition Possible Cause Action CLOSED CLOSED Normal operation Mains present Battery healthy None OPEN CLOSED Standby Mode Mains lost Battery driving load Investigate loss of mains CLOSED OPEN...

Page 4: ...e monitor disconnected or damaged PSU running in Safe Mode Check temperature sensor connections and condition of sensor Replace if suspect ON CONTINUOUS ON or OFF Internal Fault Software fault detecte...

Page 5: ...signed to support two 17 or 18 Ah batteries and as such weighs a total of 19 5 Kg when loaded Ensure that wall fixings are appropriate to support this weight 6 The product should be mounted no further...

Page 6: ...ed by conduit if it is being used to power the CIE directly 16 Fix to wall or other structure in correct orientation i e with hinge on left hand side using screws of sufficient size and length through...

Page 7: ...ling 4 Connect the EPS and PSU Fault outputs to the appropriate inputs of control equipment if remote fault monitoring is required Figure 4 Power Load and Battery connections 5 Connect the load output...

Page 8: ...4 5 14 Connect the battery temperature sensor two white wires to the PCB terminals TMP Sens See Figure 5 15 If the batteries are housed remotely replace the battery lead assembly including battery te...

Page 9: ...arts inside There is no regular maintenance required of the PSU other than periodic testing and replacement of the standby battery Reference should be made to the battery manufacturer s documentation...

Page 10: ...sposal route in accordance with all national and local regulations Before disposal of the product any batteries must be removed and disposed separately via an appropriate approved battery disposal rou...

Reviews: