6 - COMBUSTION AIR AND VENT PIPING
6.6 Condensate Piping
Use materials acceptable to authority having jurisdiction.
•
In absence of such authority:
USA - PVC or CPVC per ASTM D1785/D2845 Cement
•
or primer per ASME D2564 or F493.
Canada - CSA or ULC certifi ed PVC/CPVC pipe,
•
fi ttings and cement.
Attach PVC tee provided with boiler and fi eld sourced
•
piping to condensate drain at bottom of boiler. See
fi gure 6-1.
Slope condensate drain pipe minimum 1/4" per foot
•
(21mm/m) away from boiler.
Use fi eld source condensate pump if boiler located
•
below disposal point.
Field source condensate neutralizing kit as required
•
by authority having jurisdiction or for environmentally
friendly condensate disposal.
FIGURE 6-1 Condensate Drain
Condensate Tee
(fi eld installed)
on condensate drain
pipe
Summary of Contents for SSC Olsen OLSSC-050
Page 46: ...46 13 TROUBLE SHOOTING ...
Page 53: ...53 14 WIRING DIAGRAM 14 1 Connection Diagram ...
Page 54: ...54 14 WIRING DIAGRAM 14 2 Schematic Diagram of Ladder Form ...
Page 71: ...71 Date Service Performed Company Name Tech Initials Company Address Phone ...
Page 72: ...ECR International Inc 2201 Dwyer Avenue Utica NY 13504 4729 web site www ecrinternational com ...