4 - LOCATING BOILER
4.1 Boiler Location Considerations
• Ambient room temperature always above 32°F (0°C) to
prevent freezing of liquid condensate.
• Approved for installation in closets or alcove provided
it is correctly designed for that purpose and minimum
clearances are met.
• Protect gas ignition system components from water
(dripping, spraying, rain, etc.) during operation and
service (circulator replacement, condensate trap,
control replacement, etc.).
• Access to outdoors to meet minimum and maximum
pipe lengths for combustion air and vent piping. See
section 5.
• Disposal of condensate. See section 5.
• Drainage of water (or water - antifreeze solution)
during boiler service or from safety relief valve
discharge. See section 6.
• Access to system water piping, gas supply, and
electrical service. See sections 6, 7 and 8
.
• Clearances to combustible materials and service
clearances.
See Table 1 and Figures pg. 15.
•
Boiler shall be installed on flat vertical wall which is
capable of supporting the weight of the boiler.
• Room-sealed boiler installed in a room containing bath
or shower shall be installed so person using bath or
shower cannot touch any electrical switch or boiler
control utilizing line voltage electricity.
• Multiple Boilers can be wall mounted, placed side by
side, or back to back.
• Observe service clearances in all installations.
• For Direct Vent installations, air vents are not required
in room boiler is installed in, or when installed in closet
or compartment.
• Requires fresh air intake piped from outdoors, do not
install where air inlet is dusty or dirty.
•
Install a filter on the air intake if boiler is installed in
dusty or dirty enviroment. A high flow air filter with
minimum air filtratrion of 800 cfm can be placed on the
air intake section of the vent pipe. Boiler performance
at maximum vent length may be impacted when an air
filter is used.
• Use of unregulated gas (well gas) is not manufacturer
recomended with this boiler.
TABLE 1: BOILER CLEARANCES
Dimension
Combustible
Materials
(1)
Manufacturer
Recommended
for Service
(1)(2)
Top
0" (0 cm)
8-5/8" (220 mm)
Left Side
1-3/4" (45 mm)
1-3/4" (45 mm)
Right Side
1-3/4" (45 mm)
1-3/4" (45 mm)
Front
0" (0 mm)
17-3/4"(450 mm)
Back
0" (0 mm)
0" (0 mm)
Bottom
0" (0 mm)
*9-13/16"
(250 mm)
Combustion Air/
Vent piping
0" (0 mm)
6" (160 mm)
(1)
Required distances measured from boiler jacket.
(2)
Service, proper operation clearance recommendation.
* Allowance for piping at the bottom of boiler not included.
WARNING
Fire Hazard! Do not install on carpeting. Failure to
follow these instructions could result in death or
serious injury.
!
NOTE: Greater clearances for access should supersede fire
protection clearances.
240013501 REV A [03/15/2022]
Summary of Contents for Dunkirk DCB-100
Page 2: ...DCC 205...
Page 4: ...DCB 165...
Page 79: ...75 A 2 MODEL 75 100 Heat Only APPENDIX A WIRING DIAGRAMS 240013501 REV A 03 15 2022...
Page 80: ...76 APPENDIX A WIRING DIAGRAMS A 2 MODEL 125 Heat Only 240013501 REV A 03 15 2022...
Page 81: ...77 APPENDIX A WIRING DIAGRAMS A 3 MODEL 165 Heat Only 240013501 REV A 03 15 2022...
Page 82: ...78 APPENDIX A WIRING DIAGRAMS A 1 MODEL 115 Combi 240013501 REV A 03 15 2022...
Page 83: ...79 APPENDIX A WIRING DIAGRAMS A 4 MODEL 150 Combi 240013501 REV A 03 15 2022...
Page 84: ...80 APPENDIX A WIRING DIAGRAMS A 5 MODEL 205 Combi 240013501 REV A 03 15 2022...
Page 85: ...81 NOTES 240013501 REV A 03 15 2022...
Page 86: ...82 NOTES 240013501 REV A 03 15 2022...
Page 121: ...33 PN 240011430 REV Q 03 15 2022 75 100 HEAT ONLY WIRING DIAGRAM MODEL 75 100 HEAT ONLY...
Page 122: ...34 PN 240011430 REV Q 03 15 2022 MODEL 125 HEAT ONLY 125 HEAT ONLY WIRING DIAGRAM...
Page 123: ...35 PN 240011430 REV Q 03 15 2022 MODEL 165 HEAT ONLY 165 HEAT ONLY WIRING DIAGRAM...
Page 124: ...36 PN 240011430 REV Q 03 15 2022 115 COMBI WIRING DIAGRAM MODEL 115 COMBI...
Page 125: ...37 PN 240011430 REV Q 03 15 2022 MODEL 150 COMBI 150 COMBI WIRING DIAGRAM...
Page 126: ...38 PN 240011430 REV Q 03 15 2022 MODEL 205 COMBI 205 COMBI WIRING DIAGRAM...
Page 132: ...44 PN 240011430 REV Q 03 15 2022 LOW WATER CUTOFF DETAIL LOW WATER CUTOFF NO NO YES...
Page 137: ...49 PN 240011430 REV Q 03 15 2022 3 FAULT SOLUTION SECTIONS...