XRGI® 15 COMMISSIONING INSTRUCTION
VERSION 1.0 2019
5.1
I N S TA L L AT I O N C H E C K
5.
C O M M I S S I O N I N G X R G I ® 1 5
Before commissioning the XRGI® 15 system, retrieve the XRGI® service booklet located
inside the iQ-Control Panel. Then, fill in the system information required and fill out the
commissioning protocol. Confirm the protocol with your signature and stamp.
Start the commissioning with an installation check including:
■
Hydraulic solutions
■
Installation site
■
EC POWER Engine Coolant
■
Hydraulic connections
■
Gas-site connections
■
Flue gas-site connections
■
Electrical connections
All relevant steps for the installation check are included in the commissioning protocol
as part of the service booklet.
5.2 C O M M I S S I O N I N G
After completing and passing the installation check, the XRGI® 15 system is ready for
commissioning.
T O O L S R E Q U I R E D
■
Wrench, 11 mm
■
Allen key, 2 mm
■
Allen key, 3 mm
■
Allen key, 5 mm
■
Flue gas analyser
The XRGI® system may not be commissioned if the installation does not
comply with the installation instructions specified in the XRGI® manual
and thus, does not pass the installation check. Commissioning the XRGI®
system in spite of a failed installation check will result in loss of warranty.
Summary of Contents for XRGI 6
Page 1: ...VERSION 1 0 2019 01DOC1075 01 COMMISSIONING INSTRUCTION...
Page 2: ......
Page 14: ...XRGI COMMISSIONING INSTRUCTION VERSION 1 0 2019 12...
Page 47: ...XRGI COMMISSIONING INSTRUCTION VERSION 1 0 2019 45 N OT E S...
Page 48: ...XRGI COMMISSIONING INSTRUCTION VERSION 1 0 2019 46 N OT I Z E N...
Page 49: ......
Page 50: ...01DOC1075 01 09 2019 CO M M I S S I O N I N G I N S T R U C T I O N...