36
For RT module, if PDU is connected with the UPS, should turn the MBS to
bypass and switch off the input and then replace the EBM(s). If PDU is not
connected with the UPS, should turn off the UPS and then replace the EBM.
To replace the EBM(s):
1. Unplug the EBM power cable from the UPS.
If additional EBM(s) are installed, unplug the EBM power cable from each
EBM.
2. Replace the EBM(s). See "Recycling the used equipment" refer to chapter
7.5
for proper disposal.
A small amount of arcing may occur when connecting the EBM to UPS. This is
normal and will not harm personnel. Please connect the EBM cable to the UPS
quickly and firmly.
3. Plug the EBM cable(s) into the battery connector(s).
4. Verify that the EBM connections are tight, and there are adequate bend
radius and strain relief exist for each cable.
Testing new batteries
1. Charge the batteries for 48 hours.
2. By pressing
on the menu of “Control”.
3. Select Control then Single battery test.
The UPS can starts battery test only in line mode without active alarms.
During the battery test, the UPS transfers to Battery mode and discharges the
batteries for 10 seconds. The front panel displays
and the percentage of
the test completed.
7.5Recycling the used equipment
Contact your local recycling or hazardous waste center for information on
proper disposal of the used equipment.
Do not dispose of the batteries in the fire. Which may cause battery explosion.
The batteries must be rightly disposed according to local regulation.
Do not open or destroy the batteries. Escaping electrolyte can cause injury to
the skin and eyes. It may be toxic.
Do not discard the UPS or the UPS batteries in the trash. This product contains
sealed, lead acid batteries and must be disposed of properly. For more
information, contact your local recycling/ reuse or hazardous waste center.
Do not discard waste electrical or electronic equipment (WEEE) in the trash. For
proper disposal, contact your local recycling/reuse or hazardous waste center.
Summary of Contents for Tower 6KS
Page 1: ...Eaton 9E IN User Manual Tower 6 10K...
Page 9: ...3 2 Presentation 2 1 Front panel Tower model Tower UPS 6KS 10KS Tower UPS 6K 10K Tower EBM...
Page 11: ...5 2 3 Circuit diagram...
Page 34: ...28...
Page 36: ...30...