SECTION 5:  MAINTENANCE, 

TROUBLESHOOTING, AND REPLACEMENT

5.1  Maintenance and Care

The RTC-50 is designed to be a self-contained and maintenance-

free unit.  The printed circuit board is conformally coated at the 

factory.  The RTC-50 is intended for service by factory-trained 

personnel only.

5.2 RTC-50 Controller Troubleshooting

The Troubleshooting Guide (Table 3) is intended for service per-

sonnel to identify whether a problem being observed is external or 

internal to the unit.  For assistance with this determination, con-

tact Eaton Electrical.  If a problem is identified to be internal, the 

unit should be returned to the factory for replacement.

Table 3. Troubleshooting Guide.

5.3  Level of Repair

This manual is written with the assumption that only ATS trouble-

shooting will be performed.  If the cause of malfunction is traced 

to an RTC-50, the unit should be replaced with a new unit.  The 

malfunctioning unit should then be returned to Eaton Electrical for 

factory repairs.

5.4  RTC-50 Replacement

Step 1:  

Turn the Generator Start select to “OFF” before attempt-

ing to replace the RTC-50 controller.  Ensure all sources 

of power are removed.

Step 2:  

Disconnect the J1, J2, J3, J4, and J6 plugs from the 

controller

Step 3:  

Disconnect the wires connected to J7 and J8.

Step 4:  

Remove the four (4) screws located at the corners of the 

controller that secure it to the power panel.  Remove the 

controller.

Step 5:  

Align the new controller with the mounting holes.  Secure 

the new controller board using the existing hardware.  

Tighten the screws.

Step 6:  

Connect the J1, J2, J3, J4, and J6 plugs to their original 

receptacles.

Step 7:  

Reconnect the wires to J7 and J8.

Step 8:  

Reapply power to the transfer switch.

Step 9:  

Place the generator control selector switch in the “AUTO” 

position after the controller has been replaced.  (The Gen-

erator may start but will shut down within 5 minutes.)  

Test the system for proper functionality.

SYMPTOM

PROBABLE CAUSE

POSSIBLE SOLUTION(S)

“Util Avail” and “Gen Avail” 

LEDs are not lit.

Power is deficient or absent.

RTC-50 is malfunctioning.

Verify that power is connected 

at J1 – J4 and that it is within 

specifications.
Replace the unit.

Utility source or Generator 

source is not available when 

it should be.

Voltage is not within setpoint 

values.

Verify voltage with multimeter.  

Check the programmed setpoint 

values.

 

WARNING

HIGH VOLTAGES ARE PRESENT IN AND AROUND TRANSFER 

SWITCH EQUIPMENT.  BEFORE ATTEMPTING TO REPLACE ANY 

COMPONENT, DISCONNECT THE LINE POWER FROM THE EQUIP-

MENT BEING SERVICED BY OPENING AND LOCKING OUT, IF POSSI-

BLE, THE NEXT HIGHEST DISCONNECT DEVICE.  FAILURE TO 

FOLLOW THIS PROCEDURE COULD CAUSE SEVERE PERSONAL 

INJURY AND/OR DEATH.

ALWAYS TURN THE UTILITY POWER OFF AND TURN THE GENERA-

TOR CONTROL SELECTOR SWITCH TO THE “OFF” POSITION 

BEFORE ATTEMPTING TO REPLACE ANY COMPONENTS.

Summary of Contents for RTC-50

Page 1: ...tion Manual for the Eaton RTC 50 Automatic Transfer Switch Controller Instructional Booklet New Information Description Page 1 Introduction 2 2 Hardware Description 4 3 Operation 6 4 Programming 7 5 T...

Page 2: ...y trans fers back to the Utility and the Generator will shut down after a time delay ATSs automatically perform the transfer function and include three basic elements 1 Main contacts to connect and di...

Page 3: ...connection 1 5 Functions Features The primary function of RTC 50 controller is to accurately monitor the Utility and Generator power sources and provide the necessary intelligence to operate the ATS i...

Page 4: ...arize the reader with the RTC 50 controller hardware its nomenclature and to list the unit s specifications 2 2 LED Indicators Utility Available The green Utility Available LED illuminates if the util...

Page 5: ...tor light to indicate that routine maintenance is required for every 25 hours that the generator has run This will constitute one maintenance cycle The RTC 50 will keep track of the number of hours th...

Page 6: ...e falls below the 70 dropout level When the Generator source meets the requirements to be consid ered available the TDNE Time Delay Normal to Emergency timer will start timing TDNE is jumper programma...

Page 7: ...equency of either 50 or 60 hertz Figure 2 RTC 50 Programming Jumpers Table 2 is a summary of the Fixed and Jumper selectable settings that are available in the RTC 50 Table 2 Fixed and Jumper Selectab...

Page 8: ...Step 3 Disconnect the wires connected to J7 and J8 Step 4 Remove the four 4 screws located at the corners of the controller that secure it to the power panel Remove the controller Step 5 Align the ne...

Page 9: ...ility is available Is Generator available N ATS connects to Utility Utility Close Output closes TDNE timer times out 20 sec or 50 sec Transfer to Generator Gen Close Output closes Y Generator is power...

Page 10: ...For more information visit www eaton com IB00405004E 70 8664 Instructional Booklet Page 10 Effective June 2007 Instruction Manual for the Eaton RTC 50 Automatic Transfer Switch Controller Notes...

Page 11: ...IB00405004E 70 8664 For more information visit www eaton com Instructional Booklet Effective June 2007 Page 11 Instruction Manual for the Eaton RTC 50 Automatic Transfer Switch Controller Notes...

Page 12: ...between the purchaser and Eaton NO WARRANTIES EXPRESSED OR IMPLIED INCLUDING WAR RANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MER CHANTABILITY OR WARRANTIES ARISING FROM COURSE OF DEALING OR USAGE...

Page 13: ...para el con trolador RTC 50 del interruptor de transferencia autom tica Eaton Folleto instructivo Nueva informaci n Descripci n P gina 1 Introducci n 2 2 Descripci n del equipo 4 3 Operaci n 6 4 Prog...

Page 14: ...cuando hay dis ponible suficiente voltaje en el mismo Cuando la fuente de energ a del servicio es restaurada el ATS autom ticamente trans fiere nuevamente al servicio y el generador se interrumpe des...

Page 15: ...carga desde el servicio hacia la fuente de alimentaci n del generador Desconectado Se define desconectado cuando la entrada no est sometida a cortocircuito por un contacto o conexi n externos 1 5 Func...

Page 16: ...Indicadores con diodos emisores de luz LED Servicio disponible El diodo emisor de luz verde de disponibilidad del servicio se ilu mina si la fuente de alimentaci n del servicio cumple con los requisi...

Page 17: ...la luz indicadora del ser vicio del generador para indicar que se requiere un mantenimiento de rutina por cada 25 horas de funcionamiento del generador Esto constituir un ciclo de mantenimiento El RTC...

Page 18: ...cumple con los requisitos para ser considerada disponible el cronometraje del tiempo de demora de normal a emergencia TDNE comenzar a contar El TDNE es programable en 20 50 segundos La selec ci n de...

Page 19: ...a de 50 60 Hz Figura 2 Puentes para programaci n del RTC 50 La tabla 2 es un resumen de las selecciones fijas y seleccionables con puente que se encuentran disponibles en el RTC 50 Tabla 2 Selecciones...

Page 20: ...esquinas del controlador que lo aseguran al panel de energ a Quite el controlador Paso 5 Alinee el nuevo controlador con los agujeros de montaje Asegure el nuevo tablero del controlador utilizando la...

Page 21: ...a salida del servicio cerrado se cierra El TDNE demora del tiempo de normal a emergencia se interrumpe 20 50 segundos Transferencia al generador La salida del generador cerrado se cierra El generador...

Page 22: ...informaci n visite www eaton com IB00405004E 70 8664 Folleto instructivo P gina 10 Efectivo Junio 2007 Manual de instrucciones para el controlador RTC 50 del interruptor de transferencia autom tica E...

Page 23: ...E 70 8664 Para mayor informaci n visite www eaton com Folleto instructivo Efectivo Junio 2007 P gina 11 Manual de instrucciones para el controlador RTC 50 del interruptor de transferencia autom tica E...

Page 24: ...entre el com prador y Eaton NINGUNA GARANT A EXPRESA O IMPL CITA INCLUYENDO GARANT AS DE APTITUD PARA UN PROP SITO EN PARTICU LAR O APTITUD COMERCIAL O GARANT AS QUE SURJAN DEL CURSO DEL TRATO O USO...

Page 25: ...emploi de la commande RTC 50 pour commutateur de transfert automatique 50 Eaton Livret d instructions Nouveau document Sommaire Page 1 Introduction 2 2 Description du mat riel 4 3 Fonctionnement 6 4 P...

Page 26: ...e nouveau au r seau de distribution lectrique Un syst me intelligent active le transfert lorsque le courant sect eur est coup ou devient inf rieur une tension pr r gl e Un d marrage de moteur est alor...

Page 27: ...r des valeurs de r glage pour les sous tensions pour une dur e d pas sant de 0 5 seconde le point d expiration de la dur e de temporisa tion d urgence TDEF Transfert Changement du branchement de la ch...

Page 28: ...la commande RTC 50 ses pi ces et ses caract ristiques 2 2 Voyants DEL Disponibilit du courant secteur Le voyant DEL vert de courant secteur disponible s illumine lor sque la source de courant secteur...

Page 29: ...ecte le nombre d heures de fonctionne ment de la g n ratrice Apr s 25 heures de marche elle allume le voyant pour indiquer le besoin d entretien p riodique Ceci con stitue un cycle d entretien La comm...

Page 30: ...ratrice satisfait aux conditions exig es de disponibilit la temporisation de normal secours TDNE d bute la temporisation est programmable par cavalier 20 ou 50 secondes Le r glage 50 secondes peut tr...

Page 31: ...TC 50 Le tableau 2 est un r sum des r glages fixes et choisir avec cavaliers dans la commande RTC 50 Tableau 2 R glages fixes et choisir avec cavaliers DESCRIPTION VALEURS VALEUR PAR D FAUT USINE FIXE...

Page 32: ...fils reli s aux prises J7 et J8 tape 4 D posez les quatre 4 vis situ es aux coins de la com mande pour la fixer sur le panneau lectrique D posez la commande tape 5 Alignez la nouvelle commande sur le...

Page 33: ...ecteur la sortie de fermeture du courant secteur se ferme Temporisation de normal secours TDNE 20 ou 50 secondes Transfert vers la g n ratrice la sortie de fermeture du courant de g n ratrice se ferme...

Page 34: ...mples renseignements visitez www eaton com IB00405004E 70 8664 Livret d instructions Page 10 En vigueur d s juin 2007 Mode d emploi de la commande RTC 50 pour commutateur de transfert automatique 50 E...

Page 35: ...8664 Pour de plus amples renseignements visitez www eaton com Livret d instructions En vigueur d s juin 2007 Page 11 Mode d emploi de la commande RTC 50 pour commutateur de transfert automatique 50 E...

Page 36: ...LES GARANTIES MANANT DE CONDUITES HABITU ELLES OU D USAGE COMMERCIAL N EST TABLIE PAR RAPPORT AUX INFORMATIONS RECOMMANDATIONS ET DESCRIPTIONS CONTENUES DANS CE DOCUMENT Eaton ne peut en aucun cas tr...

Reviews: