6.0 EV charge station commissioning to a third-party (non-Eaton) CNM software
Green Motion BuildinG and Green Motion FleetcoMMissioninG Guide
IL191013EN June 2023 www.eaton.com
6.0 EV charge station commissioning to a third-party (non-Eaton)
CNM software
Follow the instructions below to commission the EV charge station to a non-Eaton CNM
software.
1.
Connect the EV charge station to the Commissioning Tool per instructions in Section 8.0.
2.
Go to Settings -> OCPP.
3.
Enter the OCPP server, authentication key, and certification details. Please contact your
CNM software provider for these details.
Figure 12. EV charge station set up in non-Eaton CNM software
4.
Reboot the EV charge station via the Commissioning Tool (Other Functions ->
Reboot EV Charge station).
5.
Disconnect the EV charge station from the Commissioning Tool by disconnecting the
RJ45 (Ethernet) cable.
Please contact your CNM software provider to claim the EV charge station.