BATTERY CABINET INSTALLATION
Eaton FERRUPS Rack Mount UPS (850 VA–7 kVA) Installation Guide
S
164201425 Rev 1
www.eaton.com/powerquality
30
8.
Attach the battery tray to the frame as shown in Figure 9.
Fit the two U-shaped brackets under the two angle rails in the
middle of the support frame. Place the battery tray back on the
frame with the weld studs aligning with the U-shaped brackets.
Secure the battery tray to the frame using four 1/4-20 hex nuts.
Battery
Tray
U-shaped Brackets
Tabs
Secure U-shaped brackets
with four 1/4-20 hex nuts
to the weld studs on
the battery tray.
Weld studs are under
the battery tray
hidden in this
view.
Figure 9. Attaching the Battery Tray to the Frame
9.
Install the battery cover on the frame as shown in Figure 10.
Pull the battery tray forward until it stops. Lift the front of the tray
and pull the tray forward again until it stops. Place the battery cover
over the frame, aligning the holes with the lip of the cover. Use four
#6-32
3/8
I
screws and internal tooth-lock washers to secure the
cover to the frame.