BATTERY CABINET INSTALLATION
Eaton FERRUPS Rack Mount UPS (850 VA–7 kVA) Installation Guide
S
164201425 Rev 1
www.eaton.com/powerquality
31
Four #6-32
3/8
I
Self-tapping screws
Four Internal tooth-lock
washers
Figure 10. Installing the Battery Cover
10.
Lift the battery cabinet and slide it into the rack until it is flush with
the rack.
Installing the Batteries in RBC-1 or RBC-2 Battery Cabinets
NOTE
Use the battery installation diagram that came with the UPS batteries and cabinet
as you follow the steps below.
To install the batteries into the RBC-1 or RBC-2 battery cabinet:
1.
Pull the battery tray out until it stops. The tray should be about half
way out.
2.
The battery cabinet chassis ground (or earth) must be connected to
the UPS chassis ground (or earth).
You must make a good connection to the battery cabinet chassis
ground (or earth). Make the ground connection at one of the screws
on the battery cabinet; to ensure a good connection, remove the
paint under the cabinet screw.
Do not make the UPS ground connection yet.
3.
Place the batteries in the cabinet according to the installation
diagram that came with the batteries.