DSH KIT (04/13)
Page 20
SYSTEM START-UP
1. Braze and check all field-made refrigerant joints for leaks and repair as necessary. See
the EarthLinked
®
Heating and Cooling System Installation, Operation and
Maintenance Manual, or the appropriate SC Quik-Start Manual or CC Quik-Start
Manual
for the proper procedure.
2.
Evacuate and charge the refrigerant system in accordance with the appropriate
EarthLinked
®
Heating and Cooling System Installation, Operation and Maintenance
Manual, or the appropriate SC Quik-Start Manual or CC Quik-Start Manual.
3. Fill the water system and ensure that all air has been eliminated from the desuperheater,
to prevent pump cavitation and bearing damage.
4. Check and repair all field-made water system joints to ensure there are no leaks.
5. Start system and check for functionality.
Summary of Contents for DSH-1872
Page 5: ...DSH KIT 04 13 Page 5 Figure 2 Desuperheater installed with GSTE Storage Water Heater...
Page 6: ...DSH KIT 04 13 Page 6 Figure 3a SC Field Wiring for Desuperheater Kit...
Page 7: ...DSH KIT 04 13 Page 7 Figure 3b CC Compressor Unit Field Wiring...
Page 11: ...DSH KIT 04 13 Page 11 Figure 4 SC Cabinet Dimensions and Connections...
Page 12: ...DSH KIT 04 13 Page 12 Figure 5 CC Cabinet Dimensions and Connections...
Page 13: ...DSH KIT 04 13 Page 13 Figure 6 SC Internal Flow Schematic with Desuperheater...
Page 14: ...DSH KIT 04 13 Page 14 Figure 7 SC Piping with Desuperheater...
Page 15: ...DSH KIT 04 13 Page 15 Figure 8 CC Internal Flow Schematic with Desuperheater...
Page 16: ...DSH KIT 04 13 Page 16 Figure 9 CC Piping with Desuperheater...