![Donaldson Torit UMA 100H Installation, Operation And Maintenance Manual Download Page 18](http://html1.mh-extra.com/html/donaldson-torit/uma-100h/uma-100h_installation-operation-and-maintenance-manual_2520677018.webp)
Installation, Operation and Maintenance Manual
Unimaster Dust Collectors – Series UMA 40-750
18
UMA 100STU, UMA 150STU and UMA 250STU
These collectors are supplied in two sections.
When the collector is fitted with an explosion relief assembly, the
explosion relief area is suitable for the collector volume only. Additional
protection may be required when mounting onto other vessels.
1 Using the sealant provided, apply two beads of sealant to the site seating
flange, one each side of the fixing holes, as shown in figure 11 (if
required, details of mounting flange fixing positions are provided in
dat
a
sheet of UMA 70-250).
2 Using the four-point lifting method, lift the bottom assembly using the lifting
brackets provided, onto the site seating flange.
3 Secure the joint with fixings to suit the application and remove excess
sealant.
4 Apply two beads of sealant to the top joint flange of the assembly, one each
side of the fixing holes.
5 Lift the combined fan and filter section, using either the four-point lifting
method or the fork lifting method, onto the bottom assembly.
6 Secure the two sections with the nuts and bolts provided and remove excess
sealant.
When the collector is fitted with an explosion relief assembly, an earthing
connection must be made between the bottom assembly and the upper
section using the earthing strap provided (see fig. 8).
INSTALLATION
Unimaster
sack tipping units