Recommissioning the System After Winterization
1. Reconnect the
from Prefiltration hose from the dock water inlet to the prefilter inlet.
Reconnect the overboard plumbing back to the unit as well.
2. Unscrew the prefilter housing(s) and discard the winterization solution that is in the filter
housing(s). Rinse the filter housing(s) with freshwater until all the solution is removed.
Completely dry the filter housing(s) and insert new filter(s) into the housing. Reinstall the filter
housings on the set prefilter bracket.
3. Fully open the concentrate valve by turning it counterclockwise. Fully close the recycle valve by
turning it clockwise. Next, turn on the water feed to the system and then provide power to the
unit. The system will turn on automatically when it detects sufficient feed water. Let the unit
flush for 30 minutes, this will remove the winterization solution.
4. After 30 minutes of flushing, power off the unit. Hook up the roduct to Tank connection, the
eed from Desalinator and reset the recycle and concentrate valves to their normal operating
positions. The unit is now ready for operation.
Remote LCD Keypad Setup
Another LCD display may be wired to the unit if a remote screen is desired in a separate location
from the unit. This display will act and function in the same manner as the master screen on the unit.
Contact your Spot Zero dealer to purchase a remote LCD display assembly.
To wire up a remote screen follow the procedure below.
Mount the remote keypad assembly in the desired location.
Run the supplied four wire cable for the remote screen from the mounting location to the unit.
Make sure that the unit is off and disconnected from the power source
The front cover of the unit s electrical box will have to be opened and the wires will need to be
hooked up to the PC board on the unit. Consult the wiring diagram of the unit on pg. 12 to see
the location of the connectors. They will have to be
the same pin connector as the
current display is using.
5. Once the connection has been made on the local display for the SZIII unit and on the remote
display the system should be ready for use. As a final check, make sure to check for loose
connections that could cause intermittent grounding or sparking.
6. Reconnect the system to power and operate the system. Either display can now be used to
navigate the systems interface and to see pressure, ppm and other operating parameters.
WARNING
ENSURE ALL OF THE PRODUCT WATER DURING THE 30 MINUTE FLUSH IS
BEING DISCARDED OVERBOARD. THIS IS NON-POTABLE, HIGH PPM WATER
AND COULD FOUL PLUMBING FIXTURES AS WELL AS DISCOLOR OR STAIN
MATERIALS IT COMES IN CONTACT WITH.
CAUTION
Make sure to watch the product to tank bulkhead on the unit for any leaks during the flush period as
this could drip on equipment or leak into the bilge.
CAUTION
To reduce the risk of electrical shock. Ensure that the unit is off, and the power is disconnected when
attempting to do electrical work on the system.
30
Summary of Contents for SPOTZERO SZIII 2000
Page 1: ...USER MANUAL INSTALLATION GUIDE SZIII 2000 3000 www spotzerowater com ...
Page 4: ... Introduction 4 ...
Page 8: ...Installation and Commissioning 8 ...
Page 13: ...13 ...
Page 17: ...Membrane Return Membrane Product assemblies Membrane Assembly 17 ...
Page 18: ...Operation and Maintenance 18 ...
Page 35: ...35 ...
Page 42: ...Troubleshooting 42 ...
Page 46: ...SZIII System Specification and Parts 46 ...
Page 47: ...47 ...
Page 48: ...48 ...
Page 49: ...49 ...
Page 50: ...50 ...
Page 51: ...51 ...
Page 52: ...52 ...
Page 53: ...53 ...
Page 54: ...54 ...
Page 55: ...Warranty 55 ...