Installing the switching power supply
SMP301
18
•
Charging process complete:
lights up yellow
•
Fault:
flashes yellow very quickly
SMP301-10
7
Installing the switching power supply
7.1
Fastening the switching power supply
When selecting the installation location, pay attention to the following instructions:
•
The switching power supply must be installed vertically on a wall (maximum
ambient temperature 50 °C) or horizontally on the ground or on a pedestal (max-
imum ambient temperature 40 °C and maximum load 75%).
•
The optimum installation position is vertically on a wall.
Item in
Element
1
Plug-in fuse F1 for output group 1 (maximum 15 A)
2
Plug-in fuse F2 for output group 2 (maximum 10 A)
3
Plug-in fuse F3 for output group 3 (maximum 7.5 A)
4
Plug-in fuse F4 for output group 4 (maximum 15 A)
5
Plug-in fuse F5 for output group 5 (maximum 15 A)
6
3x flat plug P5 6.3 mm for group 5
7
3x flat plug P4 6.3 mm for group 4
8
Flat plug P3 6.3 mm for group 3
9
Flat plug P2 6.3 mm for group 2
10
Flat plug P1 6.3 mm for group 1
11
10x flat plug P7 6.3 mm battery terminal / common earth connection
12
2x flat plug P6 for positive terminal battery
13
CI bus connection