Climbing formwork 150F
Operating the climbing formwork
35
999775002 - 02/2020
Operating the climbing formwork
Starting up
The modular design of the Climbing formwork
150F
system means that many different combinations are
possible.
Depending on the project, the actual design may differ
significantly from that described here.
➤
In these cases, you should discuss the assembly
procedure with your Doka technician.
➤
Follow the shop drawing / assembly plan.
Note:
In order to explain the entire climbing workflow as sim-
ply as possible, the repetitive actions involved are
described in detail in separate sections of this booklet.
The sections in question are:
▪
Preparing the positioning points and suspension
points (see the section headed 'Anchoring on the
structure').
▪
Closing the formwork (see the section headed 'Clos-
ing the formwork').
▪
Stripping (see the section headed 'Opening the form-
work').
▪
In addition, the following sections must also be
observed:
- Plumbing and aligning the formwork
- Repositioning by crane
NOTICE
▪
There must be a flat, firm base capable of
supporting the load.
▪
Prepare a sufficiently large assembly area.
▪
Tightening torque of the bracing tube cou-
plers: 50
Nm
For instructions on tying and joining the form-
work elements, and on cleaning them and
using concrete release agents, see the User
Information booklets 'Large-area formwork
Top50' and 'Framed formwork Framax Xlife'.
WARNING
Falling hazard!
➤
Do not step onto the pouring platforms until
the formwork is securely closed up.
Summary of Contents for 150F
Page 2: ...2 999775002 02 2020 User Information Climbing formwork 150F ...
Page 26: ...26 999775002 02 2020 Anchoring on the structure User Information Climbing formwork 150F ...
Page 34: ...34 999775002 02 2020 Repositioning User Information Climbing formwork 150F ...
Page 52: ...52 999775002 02 2020 Assembly User Information Climbing formwork 150F ...