9
COOLANT INSTALLATION
1.
Install the coolant pump by attaching it to the
mounting bracket inside the coolant tray with screws
provided.
Coolant Installation.
2.
From the rear, slide the coolant tray between the
deflector shields all the way in and under the saw
head with the coolant pump to the rear of the
machine.
3.
Fill the coolant reservoir with 20 gallons (75.7 liters)
of oil or cutting fluid recommended by the Lubrication
Chart.
DO NOT let coolant spll over the tray and
onto the floor.
The coolant pump intake must be sufficiently
submerged for coolant flow to reach all areas
n the coolant system.
PREPARATION FOR USE
1.
Check to be sure all safety guards, covers and doors
are in place, closed and/or secured.
2.
Remove the protective Saw Cap from the saw band
by opening the upper bandwheel door and carefully
pull the cap off the saw band. Then closed the
bandwheel door.
3.
Check to see that all other points listed by the
Lubrication Chart have been properly checked
and/or serviced.
Summary of Contents for TF-2025M
Page 1: ...TF 2025M Serial No 543 99101 to Band Sawing Machine Instruction Manual...
Page 5: ...MACHINE DIMENSIONS INCHES 03 MILLIMETERS 1 mm FLOOR PLAN...
Page 6: ...FRONT VIEW MACHINE DIMENSIONS Continued INCHES 03 MILLIMETERS 1 mm...
Page 7: ...MACHINE DIMENSIONS Continued SIDE VIEW INCHES 03 MILLIMETERS 1 mm...
Page 8: ...MACHINE FEATURES SIDE VIEW FRONT VIEW...
Page 9: ...MACHINE FEATURES Continued HEAD ASSEMBLY...
Page 10: ...MACHINE FEATURES Continued PROXIMITY LIMIT SWITCH LOCATIONS REAR VIEW HEAD TOP VIEW...