VI Transportation
(1) Take off all piping and wiring.
(2) Draw water out of the machine.
(3) Take off the monitor.
(4) Take off the monitor base, the signal lamp, and the upper cover.
(5) Fix the Y-axis and the Z-axis with proper fittings.
(6) Fix the transfer arm with a thin string.
(7) Put on a hanging fittings for transportation.
(8) Run a pole through the hanging fitting and raise the machine with a crane.
(9) Notes for craning:
●
Pay attention that ropes, etc. do not touch the machine.
●
Do not shock the machine.
●
Do not incline the machine excessively.
●
Do not weigh on the cover.
(10) After raising up the machine, all the jack bolts are to be pulled in to the utmost. If they
remain below the casters, it is possible to break them when the machine is placed on the
ground the next time.