INSPECTIONS
Lifting and hoisting equipment used at construction sites should always be inspected before use.
The lift should be inspected periodically, at least once a week during the work period.
If defects are discovered, they should be noted in a logbook and reported to the foreman.
FIRST INSPECTION
The Dino lifts are subjected to a first inspection and load test at the manufacturer. The results are
noted in a protocol that accompanies the lift.
DAILY INSPECTION
At the beginning of every work shift, or after the lift has been moved to another work site, the user
must always make the following inspections:
- Ascertain the carrying capacity of the ground where the lift is to be used
(refer to table on page 19)
- Check the standing stability and outriggers
- Check that the unit stands level in the horizontal plane
- Check the functioning of the emergency stop -button in both platform and chassis operating panels
- Check the functioning of the emergency descent function from both platform and chassis operating
panels
- Test alarm horn
- Inspect warning- and signal lights
- Cleanliness and function of lights and reflectors
- The condition of the operating controls and execution of the platform movements
Summary of Contents for DINO 125T
Page 2: ...DINO 125T 2...
Page 3: ...DINO 125T 3 OPERATION INSTRUCTIONS Valid from serial number 12134...
Page 6: ...DINO 125T 6 REACH DIAGRAM...
Page 13: ...DINO 125T 13 Fig 1 Fig 4 Fig 2 Fig 5 Fig 3...
Page 15: ...DINO 125T 15...
Page 18: ...DINO 125T 18...
Page 19: ...DINO 125T 19 Notes...
Page 20: ...DINO 125T 20 Fig 2 Fig 4 Fig 1 Fig 3...
Page 22: ...DINO 125T 22 Fig 2 Fig 4 Fig 1 Fig 3...
Page 24: ...DINO 125T 24...
Page 26: ...DINO 125T 26...
Page 28: ...DINO 125T 28...
Page 30: ...DINO 125T 30...
Page 32: ...DINO 125T 32...
Page 34: ...DINO 125T 34...
Page 36: ...DINO 125T 36...
Page 41: ...DINO 125T 41 340 mm...
Page 43: ...DINO 125T 43 LUBRICATION PLAN...
Page 45: ...DINO 125T 45 Fig 1 Fig 2 Fig 3...
Page 49: ...DINO 125T 49...
Page 50: ...DINO 125T 50 MUISTA PUHTAUS KOM IH G RENHET VERGESSEN NICHT REINHEIT REMEMBER CLEANLINESS...
Page 52: ...DINO 125T 52 MUISTA PUHTAUS KOM IH G RENHET VERGESSEN NICHT REINHEIT REMEMBER CLEANLINESS...
Page 54: ...DINO 125T 54 Fig 2 Fig 3 Fig 5 Fig 4 Fig 1...
Page 56: ...DINO 125T 56 Fig 2 Fig 3 Fig 5 Fig 4 Fig 1...
Page 58: ...DINO 125T 58 Fig 1 Fig 3 Fig 4 Fig 2...
Page 60: ...DINO 125T 60 Fig 1 Fig 2 Fig 3 Fig 4...
Page 62: ...DINO 125T 62 Fig 1 Fig 2...
Page 64: ...DINO 125T 64...
Page 76: ...DINO 125T 76 Muistiinpanoja Annotations Notes Notizen...
Page 78: ...DINO 125T 78 Fig 2 Fig 1...
Page 80: ...DINO 125T 80 Fig 1 Fig 2...
Page 82: ...DINO 125T 82...
Page 84: ...DINO 125T 84 Fig 2 Fig 1...
Page 87: ...DINO 125T 87 ELECTRIC SCHEME PLATFORM TURNING 12114...
Page 88: ...DINO 125T 88 ELECTRIC SCHEME 230VAC 12001...
Page 89: ...DINO 125T 89 ELECTRIC SCHEME 230VAC Lifts with no electric motor M1 12134 12141...
Page 90: ...DINO 125T 90 ELECTRIC SCHEME 12VDC 12054...
Page 91: ...DINO 125T 91 ELECTRIC SCHEME 12VDC Lifts with no electric motor M1 12134 12141...
Page 93: ...DINO 125T 93 HYDRAULIC SCHEME 12034...
Page 94: ...DINO 125T 94 Notes...