7 Commissioning
7.1 General
Once installation of the ventilation system is complete, correct
commissioning must be carried out to ensure proper function.
The system operator must use the installation instructions for
information on operating and maintenance procedures.
In the event of a defect or extraordinary circumstances (e.g. if
the system is or has been under water due to a natural disaster),
operation must be ceased immediately. Switch off the power
supply and consult an engineer.
7.2 Building requirements
The ventilation system may only be commissioned if the build-
ing / ventilated residential unit is in a ready to move in condi-
tion. Before switching on the system, all rooms must be cleared
of building dust:
Interior fittings are completely installed
Wall openings and installation shafts have been correctly
closed
Plastering, grinding and painting work is complete
Floor coverings have been fitted
Internal doors are in place
Overflow openings are present
HINWEIS
ºº
º
ºº
º
NOTE
The ventilation unit and all air inlets and outlets must be freely
accessible for commissioning.
7.3 Ventilation system
requirements
Installation of all components of the ventilation system must be
complete before commissioning can take place:
The ventilation unit and all components are installed
The condensate pipe has been connected correctly
The power supply is installed and working
Accessories are electrically connected
Air duct systems are completely installed
Air inlets and outlets are installed
Filters are in place and clean
!!
CAUTION!
Commissioning only with air ducts connected
HINWEIS
ºº
º
ºº
º
NOTE
A check must be carried out to ensure that all parts that come
into contact with the air flow are clean before switching on
the fans for the first time (additional cleaning may be re-
quired).
7.4 Engineer requirements
The trained engineer requires the following measuring equip-
ment for commissioning the ventilation system:
Multimeter
Temperature measuring device
Fan wheel anemometer with measuring funnel
Differential pressure gauge where applicable
HINWEIS
ºº
º
ºº
º
NOTE
The commissioning must be carried out by a qualified engi-
neer. Incorrect commissioning can result in inadequate venti-
lation, increased odour problems, draughts and inefficient op-
eration
7.5 Commissioning procedure
The following general procedure is used for commissioning the
ventilation system:
1) Visual inspection of the installed system
Ventilation unit, condensate connection, filters
Controller, sensors, accessories
Air duct system
Special features (e.g. fireplaces)
2) Startup
Switch on the power supply
Carry out a function check on the unit and accessories
3) Adjustment
Volume flows, setting of the unit and valves
Programming the control
4) Instruction
Instruction of the user in operation and maintenance pro-
cedures
While calibrating the ventilation system, all internal doors and
windows must be closed.
The settings required for commissioning are made in the ser-
vice menu (see Operation chapter).
The commissioning report for the ventilation systems helps to
ensure that all commissioning points are covered and docu-
mented.
HINWEIS
ºº
º
ºº
º
NOTE
Settings in the service menu have a major impact on the oper-
ation of the system and should only be carried out by a quali-
fied engineer. Improper or incorrect settings can reduce the
efficiency of the system and result in malfunctions!
HINWEIS
ºº
º
ºº
º
NOTE
Once the system is complete, there must not be any safety,
health or environmental risks. The heat recovery device man-
ufacturer is not liable for any damage.
Summary of Contents for 3VSHCE
Page 2: ......
Page 53: ...www glendimplex de DOK4SVxxDEN FD 9912 51 Domestic ventilation unit M Flex Air Plus English...
Page 54: ...52 DOK4SVxxDEN FD 9912 www glendimplex de English Domestic ventilation unit M Flex Air Plus...
Page 55: ...www glendimplex de DOK4SVxxDEN FD 9912 53 Domestic ventilation unit M Flex Air Plus English...