Operation and installation manual SOLIVIA 5.0 EU G3
In order to set up the device, follow these procedures carefully:
1. DC connection: First, connect the PV module strings to the DC disconnector (not included in
the scope of delivery).
2. Connect the DC disconnector to the solar inverter (ensure correct polarity).
3. AC connection: Please install the Wieland AC mating connector to the AC output cable and then
plug the AC connector to the solar inverter. Please make sure, that the sleeve nut is properly
fi xed and tighten.
4. Before switching on the power, check all feeders and connections one last time.
5. Close the DC disconnector.
6. Close the circuit breaker on the AC output side.
7. In case of suffi cient PV voltage (UPV > 150 V), the device now goes into the start-up mode.
8. In case of a new installation the time and date have to be set in sub-menu S (Setup) (see § 7.3.8).
All unoccupied connectors and interfaces must be sealed using the provided sealing
plugs.
6.10
Setup / settings
The default display language for solar inverters leaving the Delta factory is set to English.
After connecting to correct DC voltage and running through self-test, you will be asked to specify
the network ID and to select the desired country (countries available: Germany, France, Italy,
Spain, Greece, Portugal, Czech Republic and Belgium)).
The selection has to be confi rmed another time by the user. Once confi rmed, the network ID and
the country selection are stored to the controller memory – and the solar inverter is ready for
operation.
Please note that the enter keys on the display are locked, if there is no input entry within 5
minutes. To unlock the enter keys, you need to switch off the DC voltage and then switch it on
again.
Country selection
Increase network ID
Decrease network ID
Down *
Up *
Enter network ID
ENTER *
ESC *
Select country
Next country
Country before
Down *
Up *
ENTER *
Normal mode
* Timeout if no key is pressed (within 5 minutes)
Possible countries:
Belgium
Czech Republic
France
French island (60 Hz)
Germany
Greece continent
Greece island
Italy (50 Hz / 49 Hz)
Italy (51 Hz / 49 Hz)
Portugal
Spain (51 Hz / 49 Hz)
Spain (51 Hz / 48 Hz)
United Kingdom
Summary of Contents for SOLIVIA 5.0
Page 1: ...Operation and installation manual for SOLIVIA 5 0 EU G3 5 0 EU...
Page 2: ......
Page 4: ...2 Operation and installation manual SOLIVIA 5 0 EU G3...
Page 40: ...38 Bedienungsanleitung SOLIVIA 5 0 EU G3 Bedienungsanleitung SOLIVIA 5 0 EU G3...
Page 42: ...40 Bedienungsanleitung SOLIVIA 5 0 EU G3 Bedienungsanleitung SOLIVIA 5 0 EU G3...
Page 78: ...76 Manuale di istruzioni SOLIVIA 5 0 EU G3...
Page 80: ...78 Manuale di istruzioni SOLIVIA 5 0 EU G3...
Page 192: ...190 Manual de instru es SOLIVIA 5 0 EU G3...
Page 194: ...192 Manual de instru es SOLIVIA 5 0 EU G3...
Page 230: ...228 N vod k obsluze SOLIVIA 5 0 EU G3...
Page 232: ...230 N vod k obsluze SOLIVIA 5 0 EU G3...
Page 306: ...304 Handleiding SOLIVIA 5 0 EU G3 Handleiding SOLIVIA 5 0 EU G3...
Page 308: ...306 Handleiding SOLIVIA 5 0 EU G3 Handleiding SOLIVIA 5 0 EU G3...
Page 344: ...342 SOLIVIA 5 0 EU G3...
Page 346: ...344 SOLIVIA 5 0 EU G3...
Page 351: ...349 SOLIVIA 5 0 EU G3 4 3 1 2 3 RS485 EIA485 4 5 3 1 2 4 3 5...
Page 359: ...357 SOLIVIA 5 0 EU G3 6 9 Solar Inverter MPP Booster DC Bus DC DC DC DC A B C D AC...
Page 378: ...376 SOLIVIA 5 0 EU G3 DC 1 2 3 L1 N PE L2 N PE L3 N PE L1 N n PE L2 L3 Solivia 5 0...
Page 381: ...379 SOLIVIA 5 0 EU G3 12 https guarantee solar inverter com SOLIVIA 5 10 5...
Page 382: ...380 Operation and installation manual SOLIVIA 5 0 EU G3 13 Certificates...
Page 383: ...381 Operation and installation manual SOLIVIA 5 0 EU G3...
Page 390: ...388 Operation and installation manual SOLIVIA 5 0 EU G3 Notes...
Page 391: ......