21
STEP 13
( Lift Removal
)
1. Depress the lowering valve on the Power Unit.
2. Ensure that the lift is lowered all the way to the
ground.
3. Disconnect the Power Unit from the power source.
and/or ensure that the power to the Circuit is shut off to
prevent accidental powering on of the lift while
disassembling.
4. Disconnect the Cylinder Hoses from the Cylinder.
Hoses can be coiled and stored in the Power Unit cart.
5. Be careful to clean up any spilled hydraulic fluid that
may drip from the hose assemblies.
6. Place the Safety Lock Bars in the top column holes.
7. Remove the Lift Arm Assemblies.
8. Loosen the Anchor Bolts . Be careful not to disturbed
the lift Column until ready to move the Column.
9. Move the Column to your storage area. Secure with
straps or other device to prevent any accidental tipping
or movement of the columns during storage.
STEP 14
( Re-Installation )
1. Clear installation area of debris, tools and equipment.
2. Blow out the mounting holes with compressed air.
3. Inspect the drop in anchors for proper setting and the
concrete for defects and /or damage.
4. Line up the holes of the Base Plates with the holes.
Re-shim the lift as required to ensure the lift is installed
level.
5. With the Shims and Anchor Bolts in place, tighten all
Anchor Bolts tight to the base plate . Turn 3 to 3-3/4 Turns.
DO NOT
use an impact wrench for this procedure.
6. Follow all procedures as outlined in Steps 8 - 12.
POST-INSTALLATION CHECK-OFF
Columns Properly Shimmed And Stable
Anchor Bolts Tightened
Pivot / Sheave Pins Properly Attached
Tie Bar Straps Installed and Bolts Tight
Electric Power Supply Confirmed
Safety Lock Bars Removed
Check For Hydraulic Leaks
Oil Level Full
Lubrication of Critical Components
Check For Overhead Obstructions
Lift Arms Level
Arm Restraints Properly Adjusted
All Screws, Bolts, and Pins Secured
Surrounding Area Clean
Do not perform any maintenance or
installation of any components with out first
ensuring that electrical power has been disconnected
at the source or panel and cannot be re-energized
until all maintenance and/or installation
procedures are completed.
Before removing cylinder hoses, always ensure
that hydraulic pressure has been relieved from the
system by depressing the lowering valve until the
lift is fully lowered or the raised load is fully settled
onto the safety lock bars.
Never connect or disconnect hoses with the lift
in an elevated non-locked position.
Inspect all drop in anchors for proper setting and
or damage each time the lift is re-installed. Inspect
the concrete for cracks defects and/or damage. Do
not reinstall the lift if any of the drop in anchors are
defective or the concrete is cracked or defective.
The lift must be re-leveled, shimmed and blead each
time the lift is reinstalled. Failure to do so may result in
Injury or death.