11. The MCT 10 generates and opens the commissioning report.
e3
0b
e0
77
.1
1
12. Save and print the commissioning report. The report is required for future maintenance.
13. Close the commissioning report dialog box and the
Writing Safety Parameters
dialog box.
The safety option customization is now complete. A reset may be required depending on the safety option configuration. Up to
10 s may elapse before the safety option is ready for operation.
5.5 Commissioning Test
EN IEC 61508, EN IEC 62061 and EN ISO 13849 require that the final assembler of the machine validates the operation of the safety
function with a commissioning test. The tests for the configured safety functions are described in the commissioning report generated
by the MCT 10
Safe Plug-in
. The commissioning test must be performed in the following cases:
•
At initial start-up of the safety option.
•
After any changes related to the safety function (wiring, components, parameter settings, and more).
•
After any maintenance work related to the safety function.
The commissioning test for systems with safety functions is focused on:
•
Validating the functionality of safety monitoring and stop functions configured in the drive system.
•
Correct selection of the safety option parameter values.
•
Examining the response of specific monitoring functions to the explicit input of values outside tolerance limits.
Perform the commissioning test based on the risk analysis. Adhere all applicable standards and regulations.
5.5.1 Performing the Commissioning Test
Prerequisites:
Ensure that the following preconditions are met:
Commissioning
Installation Guide | VLT®Safety Option MCB 152