Layout

Additional refrigerant amount (R)

L2=7 m 

(Ø6.4 mm)
L3=5 m 

(Ø6.4 mm)

L1=35 m (Ø9.5 mm)

RZQG100

Case: Twin, standard liquid pipe size

1 G1 Total Ø9.5

 

=> G1=35 m

G2 Total Ø6.4 => G2=7+5=12 m

2 Case: G1>30 m

R1 Length=G1−30 m=5 m

=> R1=0.5 kg

R2 Length=G2=12 m

=> R2=0.6 kg

3 R

R=R1+R2=0.5+0.6=1.1 kg

L2=20 m 

(Ø6.4 mm)
L3=17 m 

(Ø6.4 mm)
L4=17 m 

(Ø6.4 mm)

L1=5 m (Ø9.5 mm)

RZQG125

Case: Triple, standard liquid pipe size

1 G1 Total Ø9.5 => G1=5 m

G2 Total Ø6.4 => G2=20+17+17=54 m

2 Case: G1≤30 m (and G1+G2>30 m)

R1 R1=0.0 kg

R2 Length=G1+G2−30 m=5+54−30=29

 m

=> R2=0.9 kg

3 R

R=R1+R2=0.0+0.9=0.9 kg

4.4.3

To determine the complete recharge
amount

For RZQG only: When piping length is <5 m, a complete recharge of
the unit is required.

To determine the complete recharge amount (kg) (in case of
standard liquid pipe size)

Model

Length (m)

(a)

5~10

(b)

10~20 20~30 30~40 40~50 50~60 60~75

RZQG71

1.9

2.4

2.9

3.4

3.9

RZQG100~140

3.0

3.5

4.0

4.5

5.0

5.5

6.0

R125

1.9

2.4

2.9

3.4

3.9

RZQSG140

3.0

3.5

4.0

4.5

5.0

(a)

Length = L1 (pair); L1+L2 (twin, triple); L1+L2+L4 (double
twin)

(b)

For RZQG: 3~10 m

To determine the complete recharge amount (kg) (in case of
size‑up liquid pipe size)

Model

Length (m)

(a)

3~5

5~10 10~15 15~20 20~25 25~30 30~35

RZQG71

1.9

2.4

2.9

3.4

3.9

RZQG100~140

3.0

3.5

4.0

4.5

5.0

5.5

6.0

R125

2.4

2.9

3.4

3.9

RZQSG140

3.5

4.0

4.5

5.0

(a)

Length = L1 (pair); L1+L2 (twin, triple); L1+L2+L4 (double
twin)

To determine the complete recharge amount (kg) (in case of
size‑down liquid pipe size)

Model

Length (m)

(a)

3~5

5~10

RZQG71

1.9

1.9

RZQG100~140

3.0

3.0

R125

1.9

RZQSG140

3.0

(a)

Length = L1 (pair); L1+L2 (twin, triple); L1+L2+L4 (double
twin)

4.4.4

Charging refrigerant: Setup

See 

"4.3.1 Checking refrigerant piping: Setup" on page 7

.

4.4.5

To charge additional refrigerant

WARNING

▪ Only use R410A as refrigerant. Other substances may

cause explosions and accidents.

▪ R410A  contains  fluorinated  greenhouse  gases.  Its

global  warming  potential  (GWP)  value  is  2087.5.  Do
NOT vent these gases into the atmosphere.

▪ When  charging  refrigerant,  always  use  protective

gloves and safety glasses.

Prerequisite: 

Before charging refrigerant, make sure the refrigerant

piping is connected and checked (leak test and vacuum drying).

1

Connect  the  refrigerant  cylinder  to  both  the  service  port  of  the
gas stop valve and the service port of the liquid stop valve.

2

Charge the additional refrigerant amount.

3

Open the stop valves.

4.4.6

To fix the fluorinated greenhouse gases
label

1

Fill in the label as follows:

b

Contains fluorinated greenhouse gases

2

1

1

1

2

2

kg

tCO

2

eq

GWP × kg

1000

=
=

+

kg

=

kg

=

GWP: XXX

RXXX

a

f

c

d
e

a

If a multilingual fluorinated greenhouse gases label is
delivered with the unit (see accessories), peel off the
applicable language and stick it on top of 

a

.

b

Factory refrigerant charge: see unit name plate

c

Additional refrigerant amount charged

d

Total refrigerant charge

e

Quantity of fluorinated greenhouse gases

 of the total

refrigerant charge expressed as tonnes CO

2

 equivalent.

f

GWP = Global warming potential

NOTICE

Applicable  legislation  on 

fluorinated  greenhouse  gases

requires  that  the  refrigerant  charge  of  the  unit  is  indicated
both in weight and CO

2

 equivalent.

Formula  to  calculate  the  quantity  in  CO

2

  equivalent

tonnes:

  GWP  value  of  the  refrigerant  ×  total  refrigerant

charge [in kg] / 1000

Use  the  GWP  value  mentioned  on  the  refrigerant  charge
label.  That  GWP  is  based  on  the  current  legislation  on
fluorinated greenhouse gases. The GWP mentioned in the
manual might be outdated.

2

Fix  the  label  on  the  inside  of  the  outdoor  unit.  There  is  a
dedicated place for it on the wiring diagram label.

4.5

Connecting the electrical wiring

DANGER: RISK OF ELECTROCUTION

WARNING

ALWAYS use multicore cable for power supply cables.

Summary of Contents for SkyAir RZQG140L7Y1B

Page 1: ...rs English Installation manual Split system air conditioners RZQG71L9V1B RZQG100L9V1B RZQG125L9V1B RZQG140L9V1B RZQG71L8Y1B RZQG100L8Y1B RZQG125L8Y1B RZQG140L7Y1B RZQSG100L9V1B RZQSG125L9V1B RZQSG140L...

Page 2: ...1000 1000 500 HD HU HU a b 100 100 c d e eB eD A B C D E HB HD A B C 200 300 1000 A B C E 200 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB H...

Page 3: ...aslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili on vastavuses j rgmis t e standardi te ga v i teiste normatiivsete dokumentidega kui neid kasutatakse...

Page 4: ...missioning 12 5 1 Checklist before commissioning 12 5 2 To perform a test run 12 5 3 Error codes when performing a test run 13 5 4 Dedicated field settings for technical cooling 13 6 Disposal 13 7 Tec...

Page 5: ...FORMATION The recommended height of the upper protruding part of the bolts is 20 mm 20 NOTICE Fix the outdoor unit to the foundation bolts using nuts with resin washers a If the coating on the fasteni...

Page 6: ...kout hole a in the bottom plate or cover plate by tapping on the attachment points with a flat head screwdriver and a hammer Optionally cut out the slits b with a metal saw NOTICE Precautions when mak...

Page 7: ...ressure gauge b Nitrogen c Refrigerant d Weighing machine e Vacuum pump f Stop valve g Main piping h Refrigerant branch kit i Branch piping 4 3 2 To check for leaks NOTICE Do NOT exceed the unit s max...

Page 8: ...o determine the additional refrigerant amount To determine if adding additional refrigerant is necessary If Then L1 L2 L3 L4 L5 L6 L7 chargeless length Chargeless length 10 m size down 30 m standard 1...

Page 9: ...on page 7 4 4 5 To charge additional refrigerant WARNING Only use R410A as refrigerant Other substances may cause explosions and accidents R410A contains fluorinated greenhouse gases Its global warmi...

Page 10: ...nt is connected only to a supply with a short circuit power Ssc greater than or equal to the minimum Ssc value Model Minimum Ssc value RZQG100 140_Y1 RZQSG140_Y1 1170 kVA a a This is the most stringen...

Page 11: ...G insertions can be inserted at the knockout hole When you do not use a wire conduit protect the wires with vinyl tubes to prevent the edge of the knockout hole from cutting the wires a b c d e A B A...

Page 12: ...operly earthed and the earth terminals are tightened The fuses or locally installed protection devices are installed according to this document and have NOT been bypassed The power supply voltage matc...

Page 13: ...d E7 There is a missing phase in case of three phase power supply units Note Operation will be impossible Turn OFF the power recheck the wiring and switch two of the three electrical wires L4 The air...

Page 14: ...ed air from flowing back to the suction side through the bottom of the unit 2 Maximum two units can be installed Not allowed Multiple rows of units See figure 2 on the inside of the front cover Stacke...

Page 15: ...2U Fuse F6U Fuse T 3 15 A 250 V F7U F8U Fuse F 1 0 A 250 V F1U F8U RZQG100 140_V1 RZQSG125 140_V1 F1U F4U Fuse F6U Fuse T 5 0 A 250 V F7U F8U Fuse F 1 0 A 250 V F1U F8U RZQ S G_Y1 F1U F2U Fuse 31 5 A...

Page 16: ...ical data Installation manual 16 RZQG71 140L_V1 Y1 RZQSG100 140L_V1 Y1 Split system air conditioners 4P385521 1C 2019 04 Colours BLK Black BLU Blue BRN Brown GRN Green ORG Orange RED Red WHT White YLW...

Page 17: ......

Page 18: ......

Page 19: ......

Page 20: ...4P385521 1C 2019 04 Copyright 2014 Daikin 4P385521 1 B 0000000 4P385521 1 C 0000000...

Reviews: