Commissioning

7.1

Overview: Commissioning

This  chapter  describes  what  you  have  to  do  and  know  to
commission the system after it is installed.

Typical workflow

Commissioning typically consists of the following stages:

1

Checking the "Checklist before commissioning".

2

Performing a test run for the system.

7.2

Precautions when commissioning

INFORMATION

During  the  first  running  period  of  the  unit,  the  required
power may be higher than stated on the nameplate of the
unit.  This  phenomenon  is  caused  by  the  compressor,  that
needs  a  continuous  run  time  of  50  hours  before  reaching
smooth operation and stable power consumption.

NOTICE

Before starting up the system, the unit MUST be energised
for  at  least  6  hours.  The  crankcase  heater  needs  to  heat
up  the  compressor  oil  to  avoid  oil  shortage  and
compressor breakdown during startup.

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

NOTICE

ALWAYS complete the refrigerant piping of the unit before
operating. If NOT, the compressor will break.

NOTICE

Cooling  operation  mode

.  Perform  the  test  run  in  cooling

operation mode so that stop valves failing to open can be
detected.  Even  if  the  user  interface  was  set  to  heating
operation mode, the unit will run in cooling operation mode
during 2‑3 minutes (although the user interface will display
the heating icon), and then automatically switch to heating
operation mode.

NOTICE

If  you  cannot  operate  the  unit  in  test  run,  see 

"7.5  Error

codes when performing a test run" on page 27

.

WARNING

If the panels on the indoor units are not installed yet, make
sure  to  power  OFF  the  system  after  finishing  the  test  run.
To  do  so,  turn  OFF  operation  via  the  user  interface.  Do
NOT stop operation by turning OFF the circuit breakers.

7.3

Checklist before commissioning

After  the  installation  of  the  unit,  first  check  the  items  listed  below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between the outdoor unit and the indoor unit (master)

▪ Between the indoor units

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

7.4

To perform a test run

This  task  is  only  applicable  when  using  the  BRC1E52  or  BRC1E53
user  interface.  When  using  any  other  user  interface,  see  the
installation manual or service manual of the user interface.

NOTICE

Do not interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve and gas stop valve by
removing the cap and turning counterclockwise with a
hex wrench until it stops.

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

Summary of Contents for Sky Air Alpha RZAG100N7V1B

Page 1: ...staller reference guide Sky Air Alpha series English Installer reference guide Sky Air Alpha series RZAG71N7V1B RZAG100N7V1B RZAG125N7V1B RZAG140N7V1B RZAG71N7Y1B RZAG100N7Y1B RZAG125N7Y1B RZAG140N7Y1...

Page 2: ...6 5 1 About checking the refrigerant piping 18 6 5 2 Precautions when checking the refrigerant piping 18 6 5 3 Checking refrigerant piping Setup 19 6 5 4 To check for leaks 19 6 5 5 To perform vacuum...

Page 3: ...uch the refrigerant piping water piping or internal parts during and immediately after operation It could be too hot or too cold Give it time to return to normal temperature If you must touch it wear...

Page 4: ...operated and stored MUST be larger than the minimum floor area defined in table below A m2 This applies to Indoor units without a refrigerant leakage sensor in case of indoor units with refrigerant l...

Page 5: ...ate the area immediately Possible risks Excessive refrigerant concentrations in a closed room can lead to oxygen deficiency Toxic gas may be produced if refrigerant gas comes into contact with fire DA...

Page 6: ...NG ONLY use copper wires Make sure the field wiring complies with the applicable legislation All field wiring MUST be performed in accordance with the wiring diagram supplied with the product NEVER sq...

Page 7: ...data is available on the regional Daikin website publicly accessible The full set of latest technical data is available on the Daikin Business Portal authentication required 2 2 Installer reference gu...

Page 8: ...tion R Air cooled split outdoor unit Z Inverter A Refrigerant R32 G High end series 71 140 Capacity class N7 Model series V1 Power supply 1 220 240 V 50 Hz Y1 Power supply 3N 380 415 V 50 Hz B Europea...

Page 9: ...quipment and electric wires keeping proper distances away from stereo equipment personal computers etc b a c d f e mm 1500 1500 1000 1000 1000 1000 a Earth leakage protector b Fuse c Outdoor unit d In...

Page 10: ...hat the outdoor unit is NEVER snowed up a b c c d a Snow cover or shed b Pedestal minimum height 150 mm c Prevailing wind direction d Air outlet Snow might build up and freeze between the heat exchang...

Page 11: ...s L2 L3 double twin Liquid piping 9 5 mm Gas piping 15 9 mm L1 pair twin triple double twin Model New a Existing b L1 liquid piping L1 gas piping RZAG71 Size down 6 4 mm 12 7 mm Standard 9 5 mm 15 9 m...

Page 12: ...out preparing electrical wiring INFORMATION Also read the precautions and requirements in the General safety precautions chapter INFORMATION Also read 6 7 5 Specifications of standard wiring component...

Page 13: ...e service cover is removed 6 2 2 To open the outdoor unit DANGER RISK OF ELECTROCUTION DANGER RISK OF BURNING 1 3 2 4 1 6 3 Mounting the outdoor unit 6 3 1 About mounting the outdoor unit Typical work...

Page 14: ...ollowing figure INFORMATION If necessary you can use a drain pan field supply to prevent drain water from dripping NOTICE If the unit CANNOT be installed fully level always make sure that the inclinat...

Page 15: ...Using the stop valves 6 4 2 Precautions when connecting the refrigerant piping INFORMATION Also read the precautions and requirements in the following chapters General safety precautions Preparation...

Page 16: ...ly flared in a perfect circle c Make sure the flare nut is fitted 6 4 6 To braze the pipe end The indoor unit and outdoor unit have flare connections Connect both ends without brazing If brazing shoul...

Page 17: ...5 16 5 Stem cap gas side 22 5 27 5 To handle the service cap ALWAYS use a charge hose equipped with a valve depressor pin since the service port is a Schrader type valve After handling the service po...

Page 18: ...he refrigerant piping The outdoor unit s internal refrigerant piping has been factory tested for leaks You only have to check the outdoor unit s external refrigerant piping Before checking the refrige...

Page 19: ...a manifold pressure of 0 1 MPa 1 bar 4 After turning the pump OFF check the pressure for at least 1 hour 5 If you do NOT reach the target vacuum or CANNOT maintain the vacuum for 1 hour do the follow...

Page 20: ...el and fixing it to the inside of the outdoor unit 6 6 2 About the refrigerant This product contains fluorinated greenhouse gases Do NOT vent gases into the atmosphere Refrigerant type R32 Global warm...

Page 21: ...m 20 30 m 30 40 m 40 45 m R1 0 35 kg 0 7 kg a 0 55 kg b 0 7 kg a 1 05 kg a 1 4 kg a 1 55 kg a R2 0 2 kg 0 4 kg 0 4 kg 0 6 kg 0 8 kg a 1 kg a a Only for RZAG100 140 b Only for RZAG71 In case of size up...

Page 22: ...by pressing the BS2 button once 5 Push the BS3 button once 6 When the display is not blinking anymore press the BS3 button again to activate vacuum mode To deactivate vacuum mode After charging or va...

Page 23: ...wer supply 6 7 2 About electrical compliance RZAG71 140N7V1B Equipment complying with EN IEC 61000 3 12 European International Technical Standard setting the limits for harmonic currents produced by e...

Page 24: ...cover 1 Remove the service cover See 6 2 2 To open the outdoor unit on page 13 2 Strip insulation 20 mm from the wires a b a Strip wire end to this point b Excessive strip length may cause electrical...

Page 25: ...er See 6 8 2 To close the outdoor unit on page 25 8 Connect an earth leakage circuit breaker and fuse to the power supply line 6 8 Finishing the outdoor unit installation 6 8 1 To finish the outdoor u...

Page 26: ...illed the unit must be closed Power up the unit after it is closed You read the complete installation instructions as described in the installer reference guide The indoor units are properly mounted I...

Page 27: ...g displayed the currently set temperature is not displayed The wiring is disconnected or there is a wiring error between power supply and outdoor unit between outdoor unit and indoor units between ind...

Page 28: ...a fan rotates due to strong wind it may store electricity in the capacitor or in the main circuit and cause electric shock 5 After the service is finished plug the junction connector back in Otherwise...

Page 29: ...low pressure sensor to protect the compressor by turning it OFF NEVER short circuit the low pressure switch during pump down operation 11 3 To pump down DANGER RISK OF EXPLOSION Pump down Refrigerant...

Page 30: ...row of units A E a b c d e eB eD a b c d e eB eD A B C D E B HU HD H B 100 A B C 100 1 100 100 B E 100 1000 500 A B C E 150 1 150 150 1000 500 D 500 D E 500 1000 500 B D 100 100 500 500 B D E 1 2 1 HD...

Page 31: ...tween the upper and lower units A2 Then install a roof between the upper and lower units Install the upper unit high enough above the lower unit to prevent ice buildup at the upper unit s bottom plate...

Page 32: ...6A X28A and X77A 4 Colours BLK black RED red BLU blue WHT white GRN green 4 Legend English Translation Legend Legend Field supply Field supply Optional Optional Part n Part n Description Description A...

Page 33: ...sed installer Technical skilled person who is qualified to install the product User Person who is owner of the product and or operates the product Applicable legislation All international European nat...

Page 34: ......

Page 35: ......

Page 36: ...4P573381 1 2019 04 Copyright 2019 Daikin...

Reviews: