Electrical

DANGER: RISK OF ELECTROCUTION

▪ Turn  OFF  all  power  supply  before  removing  the

switch  box  cover,  connecting  electrical  wiring  or
touching electrical parts.

▪ Disconnect  the  power  supply  for  more  than  1  minute,

and measure the voltage at the terminals of main circuit
capacitors  or  electrical  components  before  servicing.
The  voltage  MUST  be  less  than  50  V  DC  before  you
can touch electrical components. For the location of the
terminals, see the wiring diagram.

▪ Do NOT touch electrical components with wet hands.

▪ Do  NOT  leave  the  unit  unattended  when  the  service

cover is removed.

WARNING

If  NOT  factory  installed,  a  main  switch  or  other  means  for
disconnection,  having  a  contact  separation  in  all  poles
providing  full  disconnection  under  overvoltage  category  III
condition, MUST be installed in the fixed wiring.

WARNING

▪ ONLY use copper wires.

▪ Make sure the field wiring complies with the applicable

legislation.

▪ All field wiring MUST be performed in accordance with

the wiring diagram supplied with the product.

▪ NEVER  squeeze  bundled  cables  and  make  sure  they

do  NOT  come  in  contact  with  the  piping  and  sharp
edges. Make sure no external pressure is applied to the
terminal connections.

▪ Make sure to install earth wiring. Do NOT earth the unit

to  a  utility  pipe,  surge  absorber,  or  telephone  earth.
Incomplete earth may cause electrical shock.

▪ Make  sure  to  use  a  dedicated  power  circuit.  NEVER

use a power supply shared by another appliance.

▪ Make  sure  to  install  the  required  fuses  or  circuit

breakers.

▪ Make sure to install an earth leakage protector. Failure

to do so may cause electric shock or fire.

▪ When installing the earth leakage protector, make sure

it  is  compatible  with  the  inverter  (resistant  to  high
frequency electric noise) to avoid unnecessary opening
of the earth leakage protector.

CAUTION

When  connecting  the  power  supply,  the  earth  connection
must be made before the current-carrying connections are
established.  When  disconnecting  the  power  supply,  the
current-carrying connections must be separated before the
earth connection is. The length of the conductors between
the  power  supply  stress  relief  and  the  terminal  block  itself
must  be  as  such  that  the  current-carrying  wires  are
tautened before the earth wire is in case the power supply
is pulled loose from the stress relief.

NOTICE

Precautions when laying power wiring:

▪ Do  NOT  connect  wiring  of  different  thicknesses  to  the

power  terminal  block  (slack  in  the  power  wiring  may
cause abnormal heat).

▪ When  connecting  wiring  which  is  the  same  thickness,

do as shown in the figure above.

▪ For wiring, use the designated power wire and connect

firmly,  then  secure  to  prevent  outside  pressure  being
exerted on the terminal board.

▪ Use  an  appropriate  screwdriver  for  tightening  the

terminal  screws.  A  screwdriver  with  a  small  head  will
damage  the  head  and  make  proper  tightening
impossible.

▪ Over-tightening the terminal screws may break them.

WARNING

▪ After  finishing  the  electrical  work,  confirm  that  each

electrical  component  and  terminal  inside  the  electrical
components box is connected securely.

▪ Make sure all covers are closed before starting up the

unit.

NOTICE

Only applicable if the power supply is three‑phase, and the
compressor has an ON/OFF starting method.

If  there  exists  the  possibility  of  reversed  phase  after  a
momentary black out and the power goes on and off while
the  product  is  operating,  attach  a  reversed  phase
protection  circuit  locally.  Running  the  product  in  reversed
phase can break the compressor and other parts.

2

About the documentation

2.1

About this document

INFORMATION

Make sure that the user has the printed documentation and
ask him/her to keep it for future reference.

Target audience

Authorised installers

INFORMATION

This appliance is intended to be used by expert or trained
users  in  shops,  in  light  industry,  and  on  farms,  or  for
commercial and household use by lay persons.

Documentation set

This  document  is  part  of  a  documentation  set.  The  complete  set
consists of:

General safety precautions:

▪ Safety instructions that you MUST read before installing

▪ Format: Paper (in the box of the indoor unit)

Indoor unit installation manual:

▪ Installation instructions

▪ Format: Paper (in the box of the indoor unit)

Summary of Contents for Siesta ATXM25N2V1B

Page 1: ...in room air conditioner English Installer reference guide Daikin room air conditioner CTXM15N2V1B ATXM20N2V1B ATXM25N2V1B ATXM35N2V1B ATXM50N2V1B FTXM20N2V1B FTXM25N2V1B FTXM35N2V1B FTXM42N2V1B FTXM50...

Page 2: ...cting the electrical wiring 15 6 5 2 Precautions when connecting the electrical wiring 15 6 5 3 Guidelines when connecting the electrical wiring 15 6 5 4 Specifications of standard wiring components 1...

Page 3: ...ide a logbook with the product containing at least information on maintenance repair work results of tests stand by periods Also at least following information MUST be provided at an accessible place...

Page 4: ...or table to determine the minimum floor area 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 41...

Page 5: ...licable legislation WARNING Make sure there is no oxygen in the system Refrigerant may only be charged after performing the leak test and the vacuum drying In case re charge is required refer to the n...

Page 6: ...When disconnecting the power supply the current carrying connections must be separated before the earth connection is The length of the conductors between the power supply stress relief and the termi...

Page 7: ...r What to give and explain to the user Disposal How to dispose of the system Technical data Specifications of the system Glossary Definition of terms 3 About the box 3 1 Overview About the box This ch...

Page 8: ...ite Do NOT install the unit in places often used as work place In case of construction works e g grinding works where a lot of dust is created the unit MUST be covered Choose an installation location...

Page 9: ...terial with a heat transfer rate between 0 041 and 0 052 W mK 0 035 and 0 045 kcal mh C with a heat resistance of at least 120 C Insulation thickness Pipe outer diameter p Insulation inner diameter i...

Page 10: ...panel shaft 6 2 2 To re install the front panel 1 Attach the front panel Align the shafts with the slots and push them all the way in 2 Close the front panel slowly press at both sides and at the cen...

Page 11: ...on the wall using M4 25L screws field supply Class 15 42 Class 50 71 INFORMATION The removed pipe port cover can be kept in the mounting plate pocket Class 15 42 337 810 A 294 44 5 170 68 68 44 5 137...

Page 12: ...This involves General guidelines Connecting the drain piping to the indoor unit Checking for water leaks General guidelines Pipe length Keep drain piping as short as possible Pipe size If drain hose...

Page 13: ...wise water leakage may occur a b a b a Insulation fixing screw b Drain hose 4 Attach the drain hose to the refrigerant pipes bottom side using adhesive vinyl tape A B C b a A Left side piping B Left b...

Page 14: ...ther to tighten the flare nut when connecting the piping This to prevent nut cracking and leaks a b c d a Torque wrench b Spanner c Piping union d Flare nut Piping size mm Tightening torque N m Flare...

Page 15: ...fied persons in order to avoid a hazard WARNING Do NOT connect the power supply to the indoor unit This could result in electrical shock or fire WARNING Do NOT use locally purchased electrical parts i...

Page 16: ...animals that make contact with electrical parts can cause malfunctions smoke or fire a b c a Terminal block b Electrical component block c Wire retainer 5 Strip the wire ends approximately 15 mm 6 Mat...

Page 17: ...to the definition of Directive 2014 53 EU INFORMATION Install the wireless LAN adapter after finishing the indoor unit installation Refer to 6 7 2 To install the wireless LAN adapter on page 17 Basic...

Page 18: ...ccessory 2 To place the wireless LAN adapter into the unit For class 15 42 1 Place the wireless LAN adapter against the hooks 2 Lock the adapter by pressing it down 3 To remove the adapter perform the...

Page 19: ...or at least 5 seconds Result The user interface will return to the previous screen 8 Commissioning 8 1 Overview Commissioning Typical workflow Commissioning typically consists of the following stages...

Page 20: ...ormal level In cooling mode 26 28 C in heating mode 20 24 C 3 The system stops operating 3 minutes after the unit is turned OFF 8 3 1 To perform a test run using the user interface 1 Press to switch t...

Page 21: ...SWITCH E H HEATER F U FU FOR CHARACTERISTICS FUSE REFER TO PCB INSIDE YOUR UNIT FG CONNECTOR FRAME GROUND H HARNESS H P LED V L PILOT LAMP LIGHT EMITTING DIODE HAP LIGHT EMITTING DIODE SERVICE MONITOR...

Page 22: ...oduct or application explaining how to install configure and maintain it Operation manual Instruction manual specified for a certain product or application explaining how to operate it Maintenance ins...

Page 23: ......

Page 24: ...4P518023 4C 2018 09 Copyright 2018 Daikin...

Reviews: